Construction Update 9/2/2021

Phase 2:

  • The contractor began placing topsoil. Seeding and hydromulching is scheduled for the week of 9/13.
  • The irrigation contractor began repairing damaged irrigation systems. The irrigation contractor will be leaving contact information to discuss the repairs. Please continue to check your front door for this information.
  • The remaining concrete curb and gutter and concrete driveway work on Grove Street is scheduled for the week of 9/13.


Phase 3:

  • Water service installations are complete.
  • Storm sewer and sump line installation are scheduled to be complete by 9/15.
  • Street excavation is in progress on Dale Ave and will continue throughout the phase. The excavation work is expected to last through 9/15.
  • Concrete curb and gutter installation will follow street excavation and is scheduled to begin the week of 9/13.


Phase 4:

  • The watermain installation is scheduled to be complete on 9/2.
  • New water service installation is scheduled to begin the week of 9/7.
  • Following the water service installation, storm sewer work is scheduled to begin the week of 9/13.
  • Street excavation is scheduled to begin the week of 9/13 or 9/20. Removals and excavation related to the proposed sidewalk east of Code Ave is also schedule for this time frame.


Phase 5:

  • The removal of the existing Hansen Rd timber retaining wall near the CP Railroad tracks is scheduled to be complete on 9/3.
  • Retaining wall installation will begin on 9/7, and is expected to take 3 weeks.
  • See the modified Hansen Rd traffic plan for the week of 9/7 here.


Share Construction Update 9/2/2021 on Facebook Share Construction Update 9/2/2021 on Twitter Share Construction Update 9/2/2021 on Linkedin Email Construction Update 9/2/2021 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>