Construction Update 9/2/2021

Phase 2:
- The contractor began placing topsoil. Seeding and hydromulching is scheduled for the week of 9/13.
- The irrigation contractor began repairing damaged irrigation systems. The irrigation contractor will be leaving contact information to discuss the repairs. Please continue to check your front door for this information.
- The remaining concrete curb and gutter and concrete driveway work on Grove Street is scheduled for the week of 9/13.
Phase 3:
- Water service installations are complete.
- Storm sewer and sump line installation are scheduled to be complete by 9/15.
- Street excavation is in progress on Dale Ave and will continue throughout the phase. The excavation work is expected to last through 9/15.
- Concrete curb and gutter installation will follow street excavation and is scheduled to begin the week of 9/13.
Phase 4:
- The watermain installation is scheduled to be complete on 9/2.
- New water service installation is scheduled to begin the week of 9/7.
- Following the water service installation, storm sewer work is scheduled to begin the week of 9/13.
- Street excavation is scheduled to begin the week of 9/13 or 9/20. Removals and excavation related to the proposed sidewalk east of Code Ave is also schedule for this time frame.
Phase 5:
- The removal of the existing Hansen Rd timber retaining wall near the CP Railroad tracks is scheduled to be complete on 9/3.
- Retaining wall installation will begin on 9/7, and is expected to take 3 weeks.
- See the modified Hansen Rd traffic plan for the week of 9/7 here.
Share Construction Update 9/2/2021 on Facebook
Share Construction Update 9/2/2021 on Twitter
Share Construction Update 9/2/2021 on Linkedin
Email Construction Update 9/2/2021 link
Consultation has concluded