Construction Update 9/23/2021

Phase 3:

  • The storm sewer installation completion date has been extended to 9/28.
  • The street excavation completion date has been extended to 9/27.
  • Concrete curb and gutter installation will follow street excavation and is scheduled to continue the week of 9/27 on remaining phase 3 streets.
  • After the curb is installed, crews will begin grading the boulevards for topsoil placement.
  • The first lift of asphalt is scheduled for late in the week of 9/27.


Phase 4:

  • Sidewalk excavation is now anticipated to begin on 10/4, with concrete work to follow soon after.
  • The remaining storm sewer installation is expected to be complete on 9/28.
  • Street Excavation is complete on W 56th St between Code Ave and Dale Ave. The remainder of the street excavation will take place the week of 9/27.


Phase 5:

  • The temporary above ground watermain installation is in progress. Following sanitizing of the temporary system, Kusske Construction will be contacting you with a knock on the door or a notification on your door to set up temporary water service. Access to your basement is necessary to finalize the water connection.
  • The watermain installation is scheduled to begin the week of 9/27.
  • Water service installation will follow watermain installation and is anticipated to begin the week of 10/4.
Share on Facebook Share on Twitter Share on Linkedin Email this link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>