Construction Update 9/30/2021

Phase 2:

  • Brick/Paver replacement work is scheduled to begin the week of 10/4.


Phase 3:

  • The storm sewer installation and street excavation has been completed throughout the phase.
  • Concrete curb and gutter installation will begin on 10/1 (weather permitting) for W 57th St, Code Ave, and a portion of Melody Lake Dr. Check your front door for time sensitive notices.
  • After the curb is installed, crews will begin grading the boulevards for topsoil placement.
  • Topsoil placement is scheduled to begin the week of 10/4 on Dale Ave and Bernard Pl with remaining streets to follow.
  • The first lift of asphalt on Dale Ave and Bernard Pl is scheduled for Saturday, 10/2.


Phase 4:

  • Sidewalk excavation is scheduled to begin the week of 10/4, with concrete work to follow after.
  • The storm sewer installation is complete.
  • Street excavation will be completed in the phase on 9/30.


Phase 5:

  • The new watermain installation is in progress and is expected to be complete by the end of the day 10/1.
  • On 10/1, crews will begin installing new water services. The water service installations are anticipated to last through the week of 10/4. Please check your front door daily for time sensitive notifications, as you will likely lose access to your driveway for a day during this work.


The City of Edina to Dedicate Yancey Park at 4:30 p.m. Monday, 10/4.

Share on Facebook Share on Twitter Share on Linkedin Email this link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>