Construction Update 9/30/2021
Phase 2:
- Brick/Paver replacement work is scheduled to begin the week of 10/4.
Phase 3:
- The storm sewer installation and street excavation has been completed throughout the phase.
- Concrete curb and gutter installation will begin on 10/1 (weather permitting) for W 57th St, Code Ave, and a portion of Melody Lake Dr. Check your front door for time sensitive notices.
- After the curb is installed, crews will begin grading the boulevards for topsoil placement.
- Topsoil placement is scheduled to begin the week of 10/4 on Dale Ave and Bernard Pl with remaining streets to follow.
- The first lift of asphalt on Dale Ave and Bernard Pl is scheduled for Saturday, 10/2.
Phase 4:
- Sidewalk excavation is scheduled to begin the week of 10/4, with concrete work to follow after.
- The storm sewer installation is complete.
- Street excavation will be completed in the phase on 9/30.
Phase 5:
- The new watermain installation is in progress and is expected to be complete by the end of the day 10/1.
- On 10/1, crews will begin installing new water services. The water service installations are anticipated to last through the week of 10/4. Please check your front door daily for time sensitive notifications, as you will likely lose access to your driveway for a day during this work.
The City of Edina to Dedicate Yancey Park at 4:30 p.m. Monday, 10/4.
Share Construction Update 9/30/2021 on Facebook
Share Construction Update 9/30/2021 on Twitter
Share Construction Update 9/30/2021 on Linkedin
Email Construction Update 9/30/2021 link
Consultation has concluded