Construction Update 9/9/2021
Phase 2:
- Seed and hydromulch installation occurred on 9/9. Helpful tips and a short video on growing green grass can be found here.
- The remaining Grove Street concrete curb and gutter and concrete driveway work is scheduled for Saturday 9/11.
Phase 3:
- The sump drain installation is scheduled to be substantially complete on 9/10.
- Street excavation on Dale Ave is complete. The Bernard Pl street excavation is expected to be complete on 9/10. Phase wide street excavation is expected to be complete on 9/21.
- Concrete curb and gutter installation may occur on Saturday 9/11 along a portion of Dale Ave. On 9/13, curb installation will continue on streets where excavation is complete.
Phase 4:
- The watermain and water service installations are complete. Service disconnections from the temporary watermain and reconnections to the new main began.
- Storm sewer installation is scheduled to begin the week of 9/13.
- Sidewalk excavation on W. 56th St is expected to begin the week of 9/13.
Phase 5:
- The retaining wall installation is expected to be complete on 9/17.
- The contractor will begin pavement, curb, and driveway removals on 9/13.
- On 9/16 Centerpoint Energy will have a contractor on site to begin removing the old gas main.
- Watermain work is expected to begin on Hansen Rd north of the railroad tracks the week of 9/13.
- The modified Hansen Rd traffic plan will continue during the week of 9/13.
Share Construction Update 9/9/2021 on Facebook
Share Construction Update 9/9/2021 on Twitter
Share Construction Update 9/9/2021 on Linkedin
Email Construction Update 9/9/2021 link
Consultation has concluded