Construction Update 4/18/22
Phase 6 - Windsor Ave
Construction Work Resumes
On 4/15 the contractor saw cut driveways to prepare for the temporary watermain setup. The contractor will begin removing driveway and roadway pavement necessary for the watermain work during the week of 4/18.
Watermain and Temporary Water Service Update
The contractor plans to begin temporary water setup and sanitizing the week of 4/18. Kusske Construction anticipates connecting houses to the temporary water system as soon as 4/22. Please check your front door for time sensitive notices, which will include information about scheduling your temporary water hookup. The new watermain and water service installation is scheduled to finish in early May, weather permitting.
Phases 1-5
Irrigation Repairs Resume
The contractor has returned to site to continue repairing the systems damaged during construction. These repairs are expected to continue through mid May.
It's anticipated that seeding, topsoil, and hydromulch work will resume in May. Stay tuned for an updated schedule.