Welcome!
Welcome to Better Together Edina. This web page will be the hub for sharing information related to roadway reconstruction scheduled for 2027 in the Rolling Green neighborhood. Important updates will be posted on this web page at various points during the Engineering Study phase. Anticipate weekly updates during construction in 2027. Key project milestones include:
- June 2026 – Begin Engineering Study preparation
- Late summer 2026 – Informational Meeting / Video
- Nov. 2026 – Engineering Study complete
- Dec. 2026 – City Council / Public Hearing meeting to consider authorizing project design
- Mar. 2027 – City Council meeting to consider authorizing construction
- Apr. 2027 – Construction begins
- Oct. 2027 – Construction substantial completion
A series of short videos on the City's street reconstruction program can be found here.
Feel free to call or email me with your project questions, or you can post questions on this website.
We look forward to assisting and keeping you informed with this project.
Aaron Ditzler
Share Welcome! on Facebook
Share Welcome! on X (formerly Twitter)
Share Welcome! on Linkedin
Email Welcome! link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends