Construction Update - 6/16/2023

As construction begins in your phase, we would like to stress the importance of checking your front door daily for time sensitive notifications. We invite you to review this document summarizing what to expect during construction.

Phase 1: Grimes Ave and Inglewood Ave

  • Removals including curb and gutter, sidewalk and driveways is complete.
  • A select number of trees are scheduled to be removed during the week of 6/19.
  • The temporary above ground water main active.
  • Sanitary sewer repairs and water main pipe bursting began on 6/15. This work will continue through the week of 6/19.
  • Check your front door daily for temporary loss of driveway access.

Phase 2: Monterey Ave and Lynn Ave – Work tentatively scheduled to begin in July

  • A select number of tree removals will be completed in concurrence with Phase 1 tree removals, scheduled to occur the week of 6/19.

Phase 3: Kipling Ave and W 40th St – Work tentatively scheduled to begin in August

  • A select number of tree removals will be completed in concurrence with Phase 1 tree removals, scheduled to occur the week of 6/19.