Construction Update - 5/15/20

about 2 months ago

  • CenterPoint Energy crews continue to install the new gas main between France Avenue and Xerxes Avenue. Service crews began installing the new gas services between Wooddale Avenue and France Avenue.
  • Please contact CenterPoint Energy with any questions or concerns.
  • The final layer of asphalt was installed on the south parking lot of Pamela Park. Restoration and striping is tentatively scheduled for next week.
  • Watermain and sewer upgrades continue between Wooddale Avenue and France Avenue. This process will involve flushing of the main which may stir up mineral deposits. This can cause the water to appear cloudy but the water is still safe to drink. Simply run your water faucet about 1/4 turn open in a laundry room sink or tub for a few minutes to clear the water up.

Thank you for patience during this project. Have a great weekend.