  • Watermain installation continued between France Avenue and Xerxes Avenue and will continue through next week.
  • Topsoil was removed from Wooddale Avenue to France Avenue this week. Crews will continue with roadway grading in this area next week.
  • Watermain shutdown on Tuesday July 7th will affect residents on Abbott Avenue from West 56th Street to West 60th Street. This shutdown will allow City of Edina crews to make a watermain repair at West 57th Street and Abbott Avenue. Please continue to check your front door for any time sensitive notices.