Construction Update - 7/31/2020

4 days ago

  • Crews completed the grading for concrete curb and gutter between Wooddale Avenue and France Avenue.
  • Crews began installing a stormwater infiltration system between Beard Avenue and Abbott Avenue. The work will continue through next week.
  • Concrete curb will be installed on Friday, July 31 and Saturday, August 1 between Wooddale Avenue and France Avenue.
  • Watch you front doors for notices on driveway access restrictions. After concrete is poured, please do not drive across it for 5-7 days, as it needs time to gain sufficient strength.
  • Next week crews will also begin grading for the sidewalks between Wooddale Avenue and France Avenue.