  • CenterPoint Energy completed the gas main installation between Wooddale and France Aves. Service crews will begin service line work within the couple weeks.
  • CenterPoint Energy began gas main installation between France and Xerxes Aves. This work will continue over the next couple weeks.
  • Please contact CenterPoint Energy with any questions or concerns.
  • The first layer of asphalt was installed in the south lot of Pamela Park. Next week restoration will occur followed by the final asphalt layer. Striping will be installed a few days after paving is complete.
  • Watermain upgrades continue to occur between France and Wooddale Aves. Please check your doors for water shutoff notices.