Weekly Construction Update #5

Work Completed the Week of August 3rd
- Xcel Energy finished up power related relocations
- Water main connections occurred at W. 72nd/Cornelia Drive
- This work required a few different water shutdowns that affected many properties along Cornelia Drive, the project team apologizes for the duration of the experienced water outages
- Storm sewer work began on Phase 1 (W. 72nd, from Cornelia Drive to Glouchester Avenue)
Work Planned for the Week of August 10th
- Utility work will continue on Phase 1 (W. 72nd, from Cornelia Drive to Glouchester Avenue)
- As the utility work progresses to the east towards Glouchester, there may be some access restrictions to W. 72nd/Glouchester Avenue, if access to Glouchester Avenue is restricted, please use Cornelia Drive as an alternate route.
Residential Access
- Residents living on Cornelia Drive south of W. 72nd should use Glouchester Avenue for access in/out during the workday (7 am to 7 pm)
- Please reference the residential access map for suggested routes through the project area during the week of 8/10 (subject to change once the work requires access restrictions to Glouchester Avenue). This map will be updated as the project progresses.
Share Weekly Construction Update #5 on Facebook
Share Weekly Construction Update #5 on X (formerly Twitter)
Share Weekly Construction Update #5 on Linkedin
Email Weekly Construction Update #5 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends