Work Completed the Week of August 17th
- Utility work continued on Phase 1 (W. 72nd, from Cornelia Drive to Glouchester Avenue) with watermain, storm sewer and sanitary sewer replacement
- Roadway grading work began on Phase 1
- Phase 2 (W. 72nd, from Glouchester Avenue to Lynmar Lane) started with roadway removals
- Temporary water piping system was installed at Heatherton & Bristol that will supply the cul-de-sacs with water during Phase 2 utility work
- Multiple water shutdowns occurred affecting multiple properties within the project area as part of the Phase 2 start up utility work
Work Planned for the Week of August 24th
- Utility work will wrap up on Phase 1 (W. 72nd, from Cornelia Drive to Glouchester Avenue)
- Roadway grading work will wrap up on Phase 1
- Concrete curbing may get poured later in the week on Phase 1
- Utility work will continue on Phase 2 (W. 72nd, from Glouchester Avenue to Lynmar Lane)
- Cornelia Drive will be reopened prior to Cornelia Elementary school activities beginning, the roadway surface will be graveled but fully accessible from the south and from the west
Residential Access
- As the work continues to progress the project website will be updated regularly regarding access. The project team appreciates the patience and understanding during the moving operations of construction activity
Share Weekly Construction Update #7 on Facebook
Share Weekly Construction Update #7 on X (formerly Twitter)
Share Weekly Construction Update #7 on Linkedin
Email Weekly Construction Update #7 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends