Weekly Construction Update #1
Work Completed the Week of July 6
- CenterPoint Energy continued working on gas main relocations and upgrades, which required a lane closure of southbound France Avenue.
- Necessary trees, shrubs and brush were removed in the project area.
- Asphalt in pave one was turned into roadway gravel.
Work Planned for the Week of July 13
- CenterPoint Energy's will finish their work in the 72nd Street are early to mid-week.
- Xcel Energy will begin pole relocations.
- Pavement and sidewalk removals will begin in Phase 1.
- Two, large sewer bypass pipes will be set up to maintain service during construction.
- The above-ground pipe will run along the north side of 72nd Street between Oaklawn Avenue and France Avenue, and it will be buried at intersections for easier vehicle access.
- There may be some short-term intersection closures as crews bury the pipe.
Share Weekly Construction Update #1 on Facebook
Share Weekly Construction Update #1 on X (formerly Twitter)
Share Weekly Construction Update #1 on Linkedin
Email Weekly Construction Update #1 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends