Work Completed the Week of July 6

  • CenterPoint Energy continued working on gas main relocations and upgrades, which required a lane closure of southbound France Avenue.
  • Necessary trees, shrubs and brush were removed in the project area.
  • Asphalt in pave one was turned into roadway gravel.

Work Planned for the Week of July 13

  • CenterPoint Energy's will finish their work in the 72nd Street are early to mid-week.
  • Xcel Energy will begin pole relocations.
  • Pavement and sidewalk removals will begin in Phase 1.
  • Two, large sewer bypass pipes will be set up to maintain service during construction.
    • The above-ground pipe will run along the north side of 72nd Street between Oaklawn Avenue and France Avenue, and it will be buried at intersections for easier vehicle access.
    • There may be some short-term intersection closures as crews bury the pipe.