Springtime in September

3 months ago

Autumn is near but with the new grass starting to grow and the wet weather it sure feels like Spring.

On September 3rd, crews completed the grading of Beard Avenue and West 59th Street. Concrete curb and gutter installation is scheduled to begin on Monday, September 9th.

Crews also completed the topsoil installation and seeding on Ewing Avenue and Drew Avenue. They will transition to Chowen Avenue and Abbott Avenue in the coming weeks.

The new grass is starting to germinate and fill in the disturbed areas. Please refrain from walking on, mowing or disturbing the new grass. Mowing should occur when the grass reaches a height of 6 inches and at that time should be mowed to 4 inches.