Indian Hills C Neighborhood Roadway Reconstruction

Indian Hills C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes complete reconstruction of the pavement, spot replacement of concrete curb and gutter and improvements to the watermain, sanitary sewer and storm sewer systems.


Indian Hills C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes complete reconstruction of the pavement, spot replacement of concrete curb and gutter and improvements to the watermain, sanitary sewer and storm sewer systems.


  • Properly Caring for Your New Grass

    12 days ago

    Here is a short video which illustrates what you can do to get the most out of your new grass. Properly maintaining your new grass is critical, as it typically takes up to 2 years to achieve a fully mature lawn.

    Here is a short video which illustrates what you can do to get the most out of your new grass. Properly maintaining your new grass is critical, as it typically takes up to 2 years to achieve a fully mature lawn.

  • Substantial Complete

    about 1 month ago

    The project is now considered substantially complete. There are a few minor items remaining that the contractor will continue to work on in the coming weeks.

    The seeded areas will be monitored on a weekly basis to ensure proper turf establishment. Monitoring will continue into Spring 2020. Please refrain from disturbing any of the seeded areas and do not apply any fertilizers, herbicides or pesticides until Spring of 2020.

    Drew Torgerson has resigned from the City of Edina. Your new project representative is Derek Northenscold. He is a Senior Engineering Technician of 5 years with the City of Edina. If...

    The project is now considered substantially complete. There are a few minor items remaining that the contractor will continue to work on in the coming weeks.

    The seeded areas will be monitored on a weekly basis to ensure proper turf establishment. Monitoring will continue into Spring 2020. Please refrain from disturbing any of the seeded areas and do not apply any fertilizers, herbicides or pesticides until Spring of 2020.

    Drew Torgerson has resigned from the City of Edina. Your new project representative is Derek Northenscold. He is a Senior Engineering Technician of 5 years with the City of Edina. If you have any questions or concerns you can reach him at 952-826-0448 or email him at DNorthenscold@EdinaMN.gov.


  • Plantings And Punch List Repairs

    about 2 months ago

    The contractor is scheduled to begin landscaping plantings by Wed. 9/25. This may include items such as wood mulch, landscaping rock, boulders, shrubs, flowers and perennials in areas that were impacted by roadway construction.

    The contractor anticipates additional punch list repairs beginning on Saturday, 9/28.

    The plantings and punch list repair schedules are weather dependent.

    The contractor is scheduled to begin landscaping plantings by Wed. 9/25. This may include items such as wood mulch, landscaping rock, boulders, shrubs, flowers and perennials in areas that were impacted by roadway construction.

    The contractor anticipates additional punch list repairs beginning on Saturday, 9/28.

    The plantings and punch list repair schedules are weather dependent.

  • Asphalt Saw and Seal

    3 months ago

    Starting September 3rd crews will be installing joints in the asphalt pavement by sawing and installing sealant to help control pavement cracking. Please do not park on the street between 7 AM and 7 PM. Roads will remain open but there will be short delays where the work is occurring.

    Starting September 3rd crews will be installing joints in the asphalt pavement by sawing and installing sealant to help control pavement cracking. Please do not park on the street between 7 AM and 7 PM. Roads will remain open but there will be short delays where the work is occurring.

  • Grass Growing Tips

    3 months ago

    All streets are now paved with the final layer of asphalt!

    The Turf Contractor has applied hydroseed to disturbed areas. Hydroseed is a custom blend of seed, mulch and fertilizer. When mature, hydroseed provides a lawn more resistant to weather and pests.

    Tips to help grass grow.

    • Water - The contractor will continue to water the seeding for the first 90 days. The mulch bed should be moist but not over watered. Puddles = over watering. Continue to water even after grass looks established.
    • Fertilize - A commercial fertilizer is applied with the hydroseed. Additional fertilizer and herbicides are not...

    All streets are now paved with the final layer of asphalt!

    The Turf Contractor has applied hydroseed to disturbed areas. Hydroseed is a custom blend of seed, mulch and fertilizer. When mature, hydroseed provides a lawn more resistant to weather and pests.

    Tips to help grass grow.

    • Water - The contractor will continue to water the seeding for the first 90 days. The mulch bed should be moist but not over watered. Puddles = over watering. Continue to water even after grass looks established.
    • Fertilize - A commercial fertilizer is applied with the hydroseed. Additional fertilizer and herbicides are not recommended during the initial year of seeding as they can have damaging effects on grass sprouts.
    • Mowing - Do not mow new grass until it is 6" high. When grass reaches this height, mow at the highest setting. Cut with this setting for the first few months, even after grass looks established. Do not collect clippings as they help feed the soil while grass develops.
    • Preventing Weeds - Weeds will likely appear with new grass. Properly watered, mowed and fertilized grass will prevent weeds from gaining a stronghold.

    The City of Edina and Bituminous Roadways thank you for your patience and cooperation throughout the road reconstruction.


  • Construction Update

    3 months ago

    The week of August 12

    Gleason Terrace and St. Albans Circle - Monday, August 12th crews will be paving the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th.

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. Do not drive...

    The week of August 12

    Gleason Terrace and St. Albans Circle - Monday, August 12th crews will be paving the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th.

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. Do not drive on the shiny black oiled surface as this will stick to car tires and can track onto driveways. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Plantings and Restoration - If you have not yet contacted me regarding landscape plantings, please do so by Wednesday, August 14th so the contractor can schedule the planting installation. Turf areas needing topsoil and seed or touch ups have been provided to the City’s turf restoration contractor who will return to complete the work.
  • Construction Update

    4 months ago

    The week of August 5th.

    Gleason Terrace & St. Albans Circle - The contractor has tentatively scheduled the final layer of asphalt to be installed on Monday, August 12th. Please check back for updates.

    Please let me know if you have any unresolved landscaping or irrigation issues at dtorgerson@EdinaMN.gov

    The week of August 5th.

    Gleason Terrace & St. Albans Circle - The contractor has tentatively scheduled the final layer of asphalt to be installed on Monday, August 12th. Please check back for updates.

    Please let me know if you have any unresolved landscaping or irrigation issues at dtorgerson@EdinaMN.gov
  • Construction Update

    4 months ago

    Saturday and the week of July 29th

    Gleason Terrace and St Albans Circle - Saturday crews will be removing portions of cracked curb and patching some areas of asphalt. Monday July 29th crews will replace the cracked curb. Turf restoration has begun in areas disturbed by roadwork. The turf contractor will be watering these areas to establish growth.

    Saturday and the week of July 29th

    Gleason Terrace and St Albans Circle - Saturday crews will be removing portions of cracked curb and patching some areas of asphalt. Monday July 29th crews will replace the cracked curb. Turf restoration has begun in areas disturbed by roadwork. The turf contractor will be watering these areas to establish growth.

  • Construction Update

    4 months ago

    The week of July 22nd

    Gleason Terrace & St. Albans Circle – The landscaping contractor will begin work restoring disturbed landscape areas next week. If construction damaged your plants please email me the quantity and type of plants at dtorgerson@EdinaMN.gov.

    The week of July 22nd

    Gleason Terrace & St. Albans Circle – The landscaping contractor will begin work restoring disturbed landscape areas next week. If construction damaged your plants please email me the quantity and type of plants at dtorgerson@EdinaMN.gov.

  • Construction Update

    4 months ago

    Saturday & the week of July 15th

    Gleason Road – Saturday July 13th the contractor will pave the final asphalt layer patch where the two water main improvements occurred. Gleason Road will remain open in both directions during this work. Expect brief delays as the contractor will provide temporary flagging of vehicles to ensure safety and traffic flow through the area. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Gleason Terrace & St. Albans Circle – The turf establishment contractor has been approved to start placing topsoil. The start date is...

    Saturday & the week of July 15th

    Gleason Road – Saturday July 13th the contractor will pave the final asphalt layer patch where the two water main improvements occurred. Gleason Road will remain open in both directions during this work. Expect brief delays as the contractor will provide temporary flagging of vehicles to ensure safety and traffic flow through the area. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Gleason Terrace & St. Albans Circle – The turf establishment contractor has been approved to start placing topsoil. The start date is to be determined, but we anticipate their work beginning soon.