Indian Hills C Neighborhood Roadway Reconstruction

Indian Hills C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes complete reconstruction of the pavement, spot replacement of concrete curb and gutter and improvements to the watermain, sanitary sewer and storm sewer systems.


Indian Hills C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes complete reconstruction of the pavement, spot replacement of concrete curb and gutter and improvements to the watermain, sanitary sewer and storm sewer systems.


  • Asphalt Saw and Seal

    22 days ago

    Starting September 3rd crews will be installing joints in the asphalt pavement by sawing and installing sealant to help control pavement cracking. Please do not park on the street between 7 AM and 7 PM. Roads will remain open but there will be short delays where the work is occurring.

    Starting September 3rd crews will be installing joints in the asphalt pavement by sawing and installing sealant to help control pavement cracking. Please do not park on the street between 7 AM and 7 PM. Roads will remain open but there will be short delays where the work is occurring.

  • Grass Growing Tips

    about 1 month ago

    All streets are now paved with the final layer of asphalt!

    The Turf Contractor has applied hydroseed to disturbed areas. Hydroseed is a custom blend of seed, mulch and fertilizer. When mature, hydroseed provides a lawn more resistant to weather and pests.

    Tips to help grass grow.

    • Water - The contractor will continue to water the seeding for the first 90 days. The mulch bed should be moist but not over watered. Puddles = over watering. Continue to water even after grass looks established.
    • Fertilize - A commercial fertilizer is applied with the hydroseed. Additional fertilizer and herbicides are not...

    All streets are now paved with the final layer of asphalt!

    The Turf Contractor has applied hydroseed to disturbed areas. Hydroseed is a custom blend of seed, mulch and fertilizer. When mature, hydroseed provides a lawn more resistant to weather and pests.

    Tips to help grass grow.

    • Water - The contractor will continue to water the seeding for the first 90 days. The mulch bed should be moist but not over watered. Puddles = over watering. Continue to water even after grass looks established.
    • Fertilize - A commercial fertilizer is applied with the hydroseed. Additional fertilizer and herbicides are not recommended during the initial year of seeding as they can have damaging effects on grass sprouts.
    • Mowing - Do not mow new grass until it is 6" high. When grass reaches this height, mow at the highest setting. Cut with this setting for the first few months, even after grass looks established. Do not collect clippings as they help feed the soil while grass develops.
    • Preventing Weeds - Weeds will likely appear with new grass. Properly watered, mowed and fertilized grass will prevent weeds from gaining a stronghold.

    The City of Edina and Bituminous Roadways thank you for your patience and cooperation throughout the road reconstruction.


  • Construction Update

    about 1 month ago

    The week of August 12

    Gleason Terrace and St. Albans Circle - Monday, August 12th crews will be paving the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th.

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. Do not drive...

    The week of August 12

    Gleason Terrace and St. Albans Circle - Monday, August 12th crews will be paving the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th.

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. Do not drive on the shiny black oiled surface as this will stick to car tires and can track onto driveways. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Plantings and Restoration - If you have not yet contacted me regarding landscape plantings, please do so by Wednesday, August 14th so the contractor can schedule the planting installation. Turf areas needing topsoil and seed or touch ups have been provided to the City’s turf restoration contractor who will return to complete the work.
  • Construction Update

    about 2 months ago

    The week of August 5th.

    Gleason Terrace & St. Albans Circle - The contractor has tentatively scheduled the final layer of asphalt to be installed on Monday, August 12th. Please check back for updates.

    Please let me know if you have any unresolved landscaping or irrigation issues at dtorgerson@EdinaMN.gov

    The week of August 5th.

    Gleason Terrace & St. Albans Circle - The contractor has tentatively scheduled the final layer of asphalt to be installed on Monday, August 12th. Please check back for updates.

    Please let me know if you have any unresolved landscaping or irrigation issues at dtorgerson@EdinaMN.gov
  • Construction Update

    about 2 months ago

    Saturday and the week of July 29th

    Gleason Terrace and St Albans Circle - Saturday crews will be removing portions of cracked curb and patching some areas of asphalt. Monday July 29th crews will replace the cracked curb. Turf restoration has begun in areas disturbed by roadwork. The turf contractor will be watering these areas to establish growth.

    Saturday and the week of July 29th

    Gleason Terrace and St Albans Circle - Saturday crews will be removing portions of cracked curb and patching some areas of asphalt. Monday July 29th crews will replace the cracked curb. Turf restoration has begun in areas disturbed by roadwork. The turf contractor will be watering these areas to establish growth.

  • Construction Update

    2 months ago

    The week of July 22nd

    Gleason Terrace & St. Albans Circle – The landscaping contractor will begin work restoring disturbed landscape areas next week. If construction damaged your plants please email me the quantity and type of plants at dtorgerson@EdinaMN.gov.

    The week of July 22nd

    Gleason Terrace & St. Albans Circle – The landscaping contractor will begin work restoring disturbed landscape areas next week. If construction damaged your plants please email me the quantity and type of plants at dtorgerson@EdinaMN.gov.

  • Construction Update

    2 months ago

    Saturday & the week of July 15th

    Gleason Road – Saturday July 13th the contractor will pave the final asphalt layer patch where the two water main improvements occurred. Gleason Road will remain open in both directions during this work. Expect brief delays as the contractor will provide temporary flagging of vehicles to ensure safety and traffic flow through the area. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Gleason Terrace & St. Albans Circle – The turf establishment contractor has been approved to start placing topsoil. The start date is...

    Saturday & the week of July 15th

    Gleason Road – Saturday July 13th the contractor will pave the final asphalt layer patch where the two water main improvements occurred. Gleason Road will remain open in both directions during this work. Expect brief delays as the contractor will provide temporary flagging of vehicles to ensure safety and traffic flow through the area. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Gleason Terrace & St. Albans Circle – The turf establishment contractor has been approved to start placing topsoil. The start date is to be determined, but we anticipate their work beginning soon.


  • Construction Update

    3 months ago
    Flag photo

    July 4th and the week of July 8th

    Any after work non-emergency construction issues please call 952-826-1600.

    The contractor will not be working July 4th through July 7th.

    Gleason Terrace & St. Albans Circle - Next week the contractor will continue preparing the boulevard areas for topsoil.

    Have a safe and happy Independence Day!



    July 4th and the week of July 8th

    Any after work non-emergency construction issues please call 952-826-1600.

    The contractor will not be working July 4th through July 7th.

    Gleason Terrace & St. Albans Circle - Next week the contractor will continue preparing the boulevard areas for topsoil.

    Have a safe and happy Independence Day!



  • Construction Update

    3 months ago

    The week of July 1

    Gleason Terrace and St. Albans Circle – The contractor will continue preparing the boulevard areas for topsoil.

    The week of July 1

    Gleason Terrace and St. Albans Circle – The contractor will continue preparing the boulevard areas for topsoil.

  • Water Shut Off, Gleason Road Closure to Continue on June 21

    3 months ago

    Today crews replaced the water main valve on Gleason Terrace. Unfortunately the water shut off and road closure will continue tomorrow, June 21 to replace the water main valve at Saint Albans Circle. The road will remain closed overnight but local traffic will still be allowed to travel along Gleason Road north or south of Gleason Terrace and St. Albans Circle. Gleason Terrace and St. Albans Circle property owners will have access to Gleason Road during water main work. Please check front doors for water shut off notices.

    Today crews replaced the water main valve on Gleason Terrace. Unfortunately the water shut off and road closure will continue tomorrow, June 21 to replace the water main valve at Saint Albans Circle. The road will remain closed overnight but local traffic will still be allowed to travel along Gleason Road north or south of Gleason Terrace and St. Albans Circle. Gleason Terrace and St. Albans Circle property owners will have access to Gleason Road during water main work. Please check front doors for water shut off notices.