Indian Trails B & C Neighborhood Roadway Reconstruction

Indian Trails B & C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes complete reconstruction of the pavement, new concrete curb and gutter on Bello Drive, Overholt Pass and Shawnee Circle; spot replacement of curb and gutter on all other streets and improvements to the watermain, sanitary sewer and storm sewer systems.


Indian Trails B & C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes complete reconstruction of the pavement, new concrete curb and gutter on Bello Drive, Overholt Pass and Shawnee Circle; spot replacement of curb and gutter on all other streets and improvements to the watermain, sanitary sewer and storm sewer systems.


  • Construction Update

    5 days ago

    Saturday & the week of July 15th

    Shawnee Circle & Overholt Pass – Saturday July 13th the contractor will be paving the first layer of asphalt. Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt. If you anticipate you will need your vehicle during this work you...

    Saturday & the week of July 15th

    Shawnee Circle & Overholt Pass – Saturday July 13th the contractor will be paving the first layer of asphalt. Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt. If you anticipate you will need your vehicle during this work you may park on Dakota Trail but are not required to do so.

    Bello Drive, Comanche Court, Paiute Circle/Drive/Pass & Sally Lane – The turf establishment contractor has been approved to start placing topsoil. The start date is to be determined, but we anticipate their work beginning soon.



  • Construction Update

    14 days ago
    Flag photo

    July 4th and the week of July 8th

    Any after work non-emergency construction issues please call 952-826-1600.

    The contractor will not be working July 4th through July 7th.

    Comanche Court, Paiute Circle/Drive/Pass, Sally Lane - Next week the contractor will continue preparing the boulevard areas for topsoil.

    Bello Drive – The contractor has scheduled the paver driveway subcontractor to restore driveways during the week of July 8th.

    Shawnee Circle and Overholt Pass - Crews will maintain the gravel street surface over the weekend following any potential rain events and erosion. Concrete curb is scheduled for next week....

    July 4th and the week of July 8th

    Any after work non-emergency construction issues please call 952-826-1600.

    The contractor will not be working July 4th through July 7th.

    Comanche Court, Paiute Circle/Drive/Pass, Sally Lane - Next week the contractor will continue preparing the boulevard areas for topsoil.

    Bello Drive – The contractor has scheduled the paver driveway subcontractor to restore driveways during the week of July 8th.

    Shawnee Circle and Overholt Pass - Crews will maintain the gravel street surface over the weekend following any potential rain events and erosion. Concrete curb is scheduled for next week. Please remember to check front doors regularly for construction notices.

    Have a safe and happy Independence Day!


  • Shawnee Circle & Overholt Pass Concrete Postponed

    16 days ago

    Due to ongoing rain in the forecast, the crew decided to postpone the concrete curb until the week of July 8th. Rock check dams have been placed on Shawnee Circle to prevent erosion. Please check back for updates regarding concrete and asphalt paving operations.

    Due to ongoing rain in the forecast, the crew decided to postpone the concrete curb until the week of July 8th. Rock check dams have been placed on Shawnee Circle to prevent erosion. Please check back for updates regarding concrete and asphalt paving operations.

  • Construction Update

    19 days ago

    The week of July 1st

    Dave’s Sprinkler Repair, Bituminous Roadways subcontractor, is repairing irrigation systems within landscaped areas. Please check your front door and if Dave left his business card, call him to schedule a time to make the landscaped area irrigation system repair.

    Shawnee Circle & Overholt Pass – The contractor anticipates pouring concrete curb and gutter on Monday, July 1. The first layer of asphalt is scheduled to be paved the next day on Tuesday, July 2. Please continue to check your front door for any time sensitive notices.

    Bello Drive – The contractor will be installing paver...

    The week of July 1st

    Dave’s Sprinkler Repair, Bituminous Roadways subcontractor, is repairing irrigation systems within landscaped areas. Please check your front door and if Dave left his business card, call him to schedule a time to make the landscaped area irrigation system repair.

    Shawnee Circle & Overholt Pass – The contractor anticipates pouring concrete curb and gutter on Monday, July 1. The first layer of asphalt is scheduled to be paved the next day on Tuesday, July 2. Please continue to check your front door for any time sensitive notices.

    Bello Drive – The contractor will be installing paver driveway tie-ins.

    Comanche Court, Paiute Circle/Drive/Pass & Sally Lane – The contractor will continue preparing the boulevard areas for topsoil.

    Concrete Installation – After concrete curb or driveway aprons are poured, please do not drive across it for five days. The concrete needs this time to gain sufficient strength. During the time you cannot access your driveway, the Police Department will allow you to park in the street overnight in front of your home. Once the concrete curb gains sufficient strength, a temporary gravel ramp will be built across the apron so you can access your driveway. Please read the contractor notices left on front doors closely for appropriate parking locations to maintain minimum driving lanes for emergency vehicles.

  • Shawnee Circle & Overholt Pass Asphalt Milling

    20 days ago

    On Friday June 28th the contractor will be milling the asphalt surface all the way to the existing gravel base on Shawnee Circle and Overholt Pass and hauling the material away. One traffic lane will remain open during this work, and there may be brief periods when driveway access is blocked. On Saturday June 29th, the contractor will begin road excavation and installation of gravel base in preparation for concrete curb and asphalt pavement.


    On Friday June 28th the contractor will be milling the asphalt surface all the way to the existing gravel base on Shawnee Circle and Overholt Pass and hauling the material away. One traffic lane will remain open during this work, and there may be brief periods when driveway access is blocked. On Saturday June 29th, the contractor will begin road excavation and installation of gravel base in preparation for concrete curb and asphalt pavement.


  • Construction Update

    26 days ago

    Saturday June 22nd and The week of June 24th

    Bello Drive - Saturday, June 22nd, Crews will continue installing paver driveways ends and cutting the pavement to raise manhole covers. Crews will patch asphalt after this work is done.

    Comanche Court, Paiute Circle/Drive/Pass & Sally Lane - Saturday and into next week the crew will continue patching asphalt driveways, backfilling behind curbs, and preparing the boulevards for turf restoration.

    Shawnee Circle & Overholt Pass – The contractor is scheduled to begin removing the asphalt pavement late during the week of June 24. This will involve grinding and hauling away the...

    Saturday June 22nd and The week of June 24th

    Bello Drive - Saturday, June 22nd, Crews will continue installing paver driveways ends and cutting the pavement to raise manhole covers. Crews will patch asphalt after this work is done.

    Comanche Court, Paiute Circle/Drive/Pass & Sally Lane - Saturday and into next week the crew will continue patching asphalt driveways, backfilling behind curbs, and preparing the boulevards for turf restoration.

    Shawnee Circle & Overholt Pass – The contractor is scheduled to begin removing the asphalt pavement late during the week of June 24. This will involve grinding and hauling away the old material. The machine is slow moving so driveway access may be limited while it is working directly in front of driveways.

  • Gleason Road Closure Continues on June 21

    27 days ago

    Today crews replaced the water main valve on Gleason Terrace. Unfortunately the road closure will continue tomorrow, June 21 to replace the water main valve at Saint Albans Circle. The road will remain closed overnight but local traffic will still be allowed to travel along Gleason Road north or south of Gleason Terrace and St. Albans Circle.

    Today crews replaced the water main valve on Gleason Terrace. Unfortunately the road closure will continue tomorrow, June 21 to replace the water main valve at Saint Albans Circle. The road will remain closed overnight but local traffic will still be allowed to travel along Gleason Road north or south of Gleason Terrace and St. Albans Circle.

  • Gleason Road Closure

    30 days ago

    Gleason Road will be closed at the intersections of Gleason Terrace and St. Albans Circle beginning 7:00 A.M. Thursday, June 20 for water main valve replacements and will remain closed until 9:00 P.M. Thursday, June 20. Local traffic will still be allowed to travel along Gleason Road north or south of Gleason Terrace and St. Albans Circle.


    Gleason Road will be closed at the intersections of Gleason Terrace and St. Albans Circle beginning 7:00 A.M. Thursday, June 20 for water main valve replacements and will remain closed until 9:00 P.M. Thursday, June 20. Local traffic will still be allowed to travel along Gleason Road north or south of Gleason Terrace and St. Albans Circle.


  • Construction Update

    about 1 month ago

    The week of June 17th

    Pile Driving began on the Southwest Light Rail Transit project west of the Indian Trails in Eden Prairie. If you have questions or comments please contact Metro Transit at 612-373-3933.

    Bello Drive - With the first layer of asphalt placed, crews will begin installing paver driveways ends. Additionally, crews will begin preparing the boulevards for restoration. The contractor anticipates the irrigation system repairs, topsoil, landscaping and hydroseeding to begin during the week of July 1.

    Comanche Court - The first layer of asphalt is scheduled to be paved Monday, June 17th. To avoid delays on...

    The week of June 17th

    Pile Driving began on the Southwest Light Rail Transit project west of the Indian Trails in Eden Prairie. If you have questions or comments please contact Metro Transit at 612-373-3933.

    Bello Drive - With the first layer of asphalt placed, crews will begin installing paver driveways ends. Additionally, crews will begin preparing the boulevards for restoration. The contractor anticipates the irrigation system repairs, topsoil, landscaping and hydroseeding to begin during the week of July 1.

    Comanche Court - The first layer of asphalt is scheduled to be paved Monday, June 17th. To avoid delays on Monday, it’s preferred that you park on the north side of Valley View Road Sunday evening and during the day on Monday. Following paving, crews will begin preparing the boulevards for turf restoration. The contractor anticipates the irrigation system repairs, topsoil and hydroseeding to begin during the week of July 1. Next week crews will also be installing asphalt driveway ends. Driveways may be driven on 1- 2 hours after they are installed, rolled and compacted. Please note that the contractor may ask you to park on the street while this driveway work occurs.

    Paiute Circle/Drive/Pass & Sally Lane - With the first layer of asphalt placed crews will begin preparing the boulevards for turf restoration. The contractor anticipates the irrigation system repairs, topsoil and hydroseeding to begin during the week of July 1. Next week crews will also be installing asphalt driveway ends. Driveways may be driven on 1- 2 hours after they are installed, rolled and compacted. Please note that the contractor may ask you to park on the street while this driveway work occurs.

    Shawnee Circle & Overholt Pass – The contractor has suspended construction until gas service replacement by CenterPoint Energy’s contractor Michels is complete. Please continue to check back for updates.

  • Paving Update

    about 1 month ago

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Paiute Circle/Drive/Pass & Sally Lane - Paving of the first layer of asphalt will be starting on Friday, June 14 at 7 AM in Paiute Circle. Following the cul-de-sac paving the crew will transition to...

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Paiute Circle/Drive/Pass & Sally Lane - Paving of the first layer of asphalt will be starting on Friday, June 14 at 7 AM in Paiute Circle. Following the cul-de-sac paving the crew will transition to Paiute Drive, Pass and then Sally Lane.

    Comanche Court - Paving of the first layer of asphalt is scheduled to occur on either Friday, June 14 or Monday, June 17, contingent on the paving progress on Paiute Circle/Drive/Pass and Sally Lane.

    Bello Drive – It’s anticipated that crews will begin paving the first layer of asphalt Monday, June 17.