Indian Trails B & C Neighborhood Roadway Reconstruction

Indian Trails B & C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes complete reconstruction of the pavement, new concrete curb and gutter on Bello Drive, Overholt Pass and Shawnee Circle; spot replacement of curb and gutter on all other streets and improvements to the watermain, sanitary sewer and storm sewer systems.


Indian Trails B & C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes complete reconstruction of the pavement, new concrete curb and gutter on Bello Drive, Overholt Pass and Shawnee Circle; spot replacement of curb and gutter on all other streets and improvements to the watermain, sanitary sewer and storm sewer systems.


  • Properly Caring for Your New Grass

    12 days ago

    Here is a short video which illustrates what you can do to get the most out of your new grass. Properly maintaining your new grass is critical, as it typically takes up to 2 years to achieve a fully mature lawn.

    Here is a short video which illustrates what you can do to get the most out of your new grass. Properly maintaining your new grass is critical, as it typically takes up to 2 years to achieve a fully mature lawn.

  • Substantial Completion

    about 1 month ago

    The project is now considered substantially complete. There are a few minor items remaining that the contractor will continue to work on in the coming weeks.

    The seeded areas will be monitored on a weekly basis to ensure proper turf establishment. Monitoring will continue into Spring 2020. Please refrain from disturbing any of the seeded areas and do not apply any fertilizers, herbicides or pesticides until Spring of 2020.

    Drew Torgerson has resigned from the City of Edina. Your new project representative is Derek Northenscold. He is a Senior Engineering Technician of 5 years with the City of Edina....

    The project is now considered substantially complete. There are a few minor items remaining that the contractor will continue to work on in the coming weeks.

    The seeded areas will be monitored on a weekly basis to ensure proper turf establishment. Monitoring will continue into Spring 2020. Please refrain from disturbing any of the seeded areas and do not apply any fertilizers, herbicides or pesticides until Spring of 2020.

    Drew Torgerson has resigned from the City of Edina. Your new project representative is Derek Northenscold. He is a Senior Engineering Technician of 5 years with the City of Edina. If you have any questions or concerns you can reach him at 952-826-0448 or email him at DNorthenscold@EdinaMN.gov.

  • Plantings and Punch List Repairs

    about 2 months ago

    The contractor is scheduled to begin landscaping plantings by Wed. 9/25. This may include items such as wood mulch, landscaping rock, boulders, shrubs, flowers and perennials in areas that were impacted by roadway construction.

    The contractor anticipates additional punch list repairs beginning on Saturday, 9/28.

    The plantings and punch list repair schedules are weather dependent.

    The contractor is scheduled to begin landscaping plantings by Wed. 9/25. This may include items such as wood mulch, landscaping rock, boulders, shrubs, flowers and perennials in areas that were impacted by roadway construction.

    The contractor anticipates additional punch list repairs beginning on Saturday, 9/28.

    The plantings and punch list repair schedules are weather dependent.
  • Asphalt Saw and Seal

    3 months ago

    Starting September 3rd crews will be installing joints in the asphalt pavement by sawing and installing sealant to help control pavement cracking. Please do not park on the street between 7 AM and 7 PM. Roads will remain open but there will be short delays where the work is occurring.

    Starting September 3rd crews will be installing joints in the asphalt pavement by sawing and installing sealant to help control pavement cracking. Please do not park on the street between 7 AM and 7 PM. Roads will remain open but there will be short delays where the work is occurring.

  • Grass Growing Tips

    3 months ago

    All streets are now paved with the final layer of asphalt!

    The Turf Contractor has applied hydroseed to disturbed areas. Hydroseed is a custom blend of seed, mulch and fertilizer. When mature, hydroseed provides a lawn more resistant to weather and pests.

    Tips to help grass grow.

    • Water - The contractor will continue to water the seeding for the first 90 days. The mulch bed should be moist but not over watered. Puddles = over watering. Continue to water even after grass looks established.
    • Fertilize - A commercial fertilizer is applied with the hydroseed. Additional fertilizer and herbicides...

    All streets are now paved with the final layer of asphalt!

    The Turf Contractor has applied hydroseed to disturbed areas. Hydroseed is a custom blend of seed, mulch and fertilizer. When mature, hydroseed provides a lawn more resistant to weather and pests.

    Tips to help grass grow.

    • Water - The contractor will continue to water the seeding for the first 90 days. The mulch bed should be moist but not over watered. Puddles = over watering. Continue to water even after grass looks established.
    • Fertilize - A commercial fertilizer is applied with the hydroseed. Additional fertilizer and herbicides are not recommended during the initial year of seeding as they can have damaging effects on grass sprouts.
    • Mowing - Do not mow new grass until it is 6" high. When grass reaches this height, mow at the highest setting. Cut with this setting for the first few months, even after grass looks established. Do not collect clippings as they help feed the soil while grass develops.
    • Preventing Weeds - Weeds will likely appear with new grass. Properly watered, mowed and fertilized grass will prevent weeds from gaining a stronghold.

    The City of Edina and Bituminous Roadways thank you for your patience and cooperation throughout the road reconstruction.

  • Construction Update

    3 months ago

    The week of August 12th

    Bello Drive - Monday, August 12th crews will pave the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th.

    Overholt Pass, and Shawnee Circle - Monday, August 12th crews will be paving the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th. Visu Sewer will be lining the sanitary sewer Monday, August 12th and Wednesday, August 14th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer...

    The week of August 12th

    Bello Drive - Monday, August 12th crews will pave the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th.

    Overholt Pass, and Shawnee Circle - Monday, August 12th crews will be paving the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th. Visu Sewer will be lining the sanitary sewer Monday, August 12th and Wednesday, August 14th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

    Paiute Drive - Visu Sewer will be lining the sanitary sewer Monday, August 12th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

    Sally Lane - Visu Sewer will be lining the sanitary sewer Wednesday, August 14th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt. Prior to paving, a liquid asphalt material is placed on the driving surface immediately prior to paving to help bond the initial and final pavement layers together. Please do not drive on this shiny black oil material or it will stick to car tires, fenders and can track onto driveways and is very difficult to remove.

    Plantings and Restoration - If you have not yet contacted me regarding landscape plantings, please do so by Wednesday, August 14th so the contractor can schedule the planting installation. Turf areas needing topsoil and seed or touch ups have been provided to the City’s turf restoration contractor who will return to complete the work. Please recall CenterPoint will be doing their own restoration due to the gas main and service replacement. Those areas began and are noted by the light brown colored erosion blanket.

  • Construction Update

    4 months ago

    The week of August 5th.

    Paiute /Drive/Pass and Sally Lane - Visu Sewer will be lining the sanitary sewer via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

    Shawnee Circle and Overholt Pass - Monday August 5th crews will preparing to install asphalt driveway ends. Installation of the asphalt is scheduled for Tuesday and Wednesday....

    The week of August 5th.

    Paiute /Drive/Pass and Sally Lane - Visu Sewer will be lining the sanitary sewer via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

    Shawnee Circle and Overholt Pass - Monday August 5th crews will preparing to install asphalt driveway ends. Installation of the asphalt is scheduled for Tuesday and Wednesday. Driveways may be driven on 1- 2 hours after they are installed, rolled and compacted. Please note that the contractor may ask you to park on the street while this driveway work occurs. Additionally, the contractor has tentatively scheduled the final layer of asphalt to be installed on Monday, August 12th. Please check back for updates.

    Bello Drive - The contractor has tentatively scheduled the final layer of asphalt to be installed on Monday, August 12th. Please check back for updates.

    Please let me know if you have any unresolved landscaping or irrigation issues at dtorgerson@EdinaMN.gov

  • Paving Update - Comanche Ct, Paiute Circle/Drive/Pass, and Sally Lane

    4 months ago

    The contractor notified the City that paving of the final layer of asphalt on Comanche Court, Paiute Circle, Paiute Drive, Paiute Pass, and Sally Lane will occur tomorrow August 1st.

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. Do not drive on the shiny black oiled surface as...

    The contractor notified the City that paving of the final layer of asphalt on Comanche Court, Paiute Circle, Paiute Drive, Paiute Pass, and Sally Lane will occur tomorrow August 1st.

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. Do not drive on the shiny black oiled surface as this will stick to car tires and can track onto driveways. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

  • Construction Update

    4 months ago

    Saturday & the week of July 29th

    Shawnee Circle & Overholt Pass – Notices have been left at front doors regarding concrete curb and driveway apron work scheduled for Monday, July 29th. Please see notice for parking information during and after concrete work.

    Concrete Installation - Wherever concrete driveway aprons or surfaces are poured, please do not drive across it for five days. The concrete needs this time to gain sufficient strength. During the time you cannot access your driveway, the Police Department will allow you to park in the street overnight in front of your home. Once the concrete...

    Saturday & the week of July 29th

    Shawnee Circle & Overholt Pass – Notices have been left at front doors regarding concrete curb and driveway apron work scheduled for Monday, July 29th. Please see notice for parking information during and after concrete work.

    Concrete Installation - Wherever concrete driveway aprons or surfaces are poured, please do not drive across it for five days. The concrete needs this time to gain sufficient strength. During the time you cannot access your driveway, the Police Department will allow you to park in the street overnight in front of your home. Once the concrete curb gains sufficient strength, a temporary gravel ramp will be built across the apron so you can access your driveway. Please read the contractor notices closely for appropriate parking locations to maintain minimum driving lanes for emergency vehicles.

    Bello Drive, Comanche Court, Paiute Circle/Drive/Pass & Sally Lane – Saturday crews will be removing portions of cracked curb and patching some areas of asphalt. Monday July 29th crews will replace the cracked curb. Turf restoration has begun in areas disturbed by roadwork. The turf contractor will be watering these areas to establish growth.The portions of yard still filled with sand will be restored with seed by CenterPoint Energy.

    If you are still owed plants or irrigation repairs due to construction please email me at dtorgerson@EdinaMN.gov.


  • Construction Update

    4 months ago

    Saturday & the week of July 22nd

    Shawnee Circle & Overholt Pass – Saturday July 20th the contractor will be paving the patch on Dakota Trail. Dakota trail, Overholt Pass and Shawnee Circle will remain open during this work but there may be short delays during the work. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Bello Drive, Comanche Court, Paiute Circle/Drive/Pass & Sally Lane – The landscaping contractor will begin work restoring disturbed landscape areas next week. If construction damaged your plants please email me the quantity and type of...

    Saturday & the week of July 22nd

    Shawnee Circle & Overholt Pass – Saturday July 20th the contractor will be paving the patch on Dakota Trail. Dakota trail, Overholt Pass and Shawnee Circle will remain open during this work but there may be short delays during the work. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Bello Drive, Comanche Court, Paiute Circle/Drive/Pass & Sally Lane – The landscaping contractor will begin work restoring disturbed landscape areas next week. If construction damaged your plants please email me the quantity and type of plants at dtorgerson@EdinaMN.gov.