Construction Update

4 months ago

The week of August 5th.

Paiute /Drive/Pass and Sally Lane - Visu Sewer will be lining the sanitary sewer via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

Shawnee Circle and Overholt Pass - Monday August 5th crews will preparing to install asphalt driveway ends. Installation of the asphalt is scheduled for Tuesday and Wednesday. Driveways may be driven on 1- 2 hours after they are installed, rolled and compacted. Please note that the contractor may ask you to park on the street while this driveway work occurs. Additionally, the contractor has tentatively scheduled the final layer of asphalt to be installed on Monday, August 12th. Please check back for updates.

Bello Drive - The contractor has tentatively scheduled the final layer of asphalt to be installed on Monday, August 12th. Please check back for updates.

Please let me know if you have any unresolved landscaping or irrigation issues at dtorgerson@EdinaMN.gov