Construction Update

4 months ago

The week of August 12th

Bello Drive - Monday, August 12th crews will pave the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th.

Overholt Pass, and Shawnee Circle - Monday, August 12th crews will be paving the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th. Visu Sewer will be lining the sanitary sewer Monday, August 12th and Wednesday, August 14th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

Paiute Drive - Visu Sewer will be lining the sanitary sewer Monday, August 12th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

Sally Lane - Visu Sewer will be lining the sanitary sewer Wednesday, August 14th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt. Prior to paving, a liquid asphalt material is placed on the driving surface immediately prior to paving to help bond the initial and final pavement layers together. Please do not drive on this shiny black oil material or it will stick to car tires, fenders and can track onto driveways and is very difficult to remove.

Plantings and Restoration - If you have not yet contacted me regarding landscape plantings, please do so by Wednesday, August 14th so the contractor can schedule the planting installation. Turf areas needing topsoil and seed or touch ups have been provided to the City’s turf restoration contractor who will return to complete the work. Please recall CenterPoint will be doing their own restoration due to the gas main and service replacement. Those areas began and are noted by the light brown colored erosion blanket.