Indian Trails B & C Neighborhood Roadway Reconstruction

Indian Trails B & C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes complete reconstruction of the pavement, new concrete curb and gutter on Bello Drive, Overholt Pass and Shawnee Circle; spot replacement of curb and gutter on all other streets and improvements to the watermain, sanitary sewer and storm sewer systems.


Indian Trails B & C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes complete reconstruction of the pavement, new concrete curb and gutter on Bello Drive, Overholt Pass and Shawnee Circle; spot replacement of curb and gutter on all other streets and improvements to the watermain, sanitary sewer and storm sewer systems.


  • Grass Growing Tips

    8 days ago

    All streets are now paved with the final layer of asphalt!

    The Turf Contractor has applied hydroseed to disturbed areas. Hydroseed is a custom blend of seed, mulch and fertilizer. When mature, hydroseed provides a lawn more resistant to weather and pests.

    Tips to help grass grow.

    • Water - The contractor will continue to water the seeding for the first 90 days. The mulch bed should be moist but not over watered. Puddles = over watering. Continue to water even after grass looks established.
    • Fertilize - A commercial fertilizer is applied with the hydroseed. Additional fertilizer and herbicides...

    All streets are now paved with the final layer of asphalt!

    The Turf Contractor has applied hydroseed to disturbed areas. Hydroseed is a custom blend of seed, mulch and fertilizer. When mature, hydroseed provides a lawn more resistant to weather and pests.

    Tips to help grass grow.

    • Water - The contractor will continue to water the seeding for the first 90 days. The mulch bed should be moist but not over watered. Puddles = over watering. Continue to water even after grass looks established.
    • Fertilize - A commercial fertilizer is applied with the hydroseed. Additional fertilizer and herbicides are not recommended during the initial year of seeding as they can have damaging effects on grass sprouts.
    • Mowing - Do not mow new grass until it is 6" high. When grass reaches this height, mow at the highest setting. Cut with this setting for the first few months, even after grass looks established. Do not collect clippings as they help feed the soil while grass develops.
    • Preventing Weeds - Weeds will likely appear with new grass. Properly watered, mowed and fertilized grass will prevent weeds from gaining a stronghold.

    The City of Edina and Bituminous Roadways thank you for your patience and cooperation throughout the road reconstruction.

  • Construction Update

    15 days ago

    The week of August 12th

    Bello Drive - Monday, August 12th crews will pave the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th.

    Overholt Pass, and Shawnee Circle - Monday, August 12th crews will be paving the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th. Visu Sewer will be lining the sanitary sewer Monday, August 12th and Wednesday, August 14th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer...

    The week of August 12th

    Bello Drive - Monday, August 12th crews will pave the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th.

    Overholt Pass, and Shawnee Circle - Monday, August 12th crews will be paving the final layer of asphalt. Please have all cars off the street by 7:00 A.M. Monday, August 12th. Visu Sewer will be lining the sanitary sewer Monday, August 12th and Wednesday, August 14th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

    Paiute Drive - Visu Sewer will be lining the sanitary sewer Monday, August 12th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

    Sally Lane - Visu Sewer will be lining the sanitary sewer Wednesday, August 14th via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt. Prior to paving, a liquid asphalt material is placed on the driving surface immediately prior to paving to help bond the initial and final pavement layers together. Please do not drive on this shiny black oil material or it will stick to car tires, fenders and can track onto driveways and is very difficult to remove.

    Plantings and Restoration - If you have not yet contacted me regarding landscape plantings, please do so by Wednesday, August 14th so the contractor can schedule the planting installation. Turf areas needing topsoil and seed or touch ups have been provided to the City’s turf restoration contractor who will return to complete the work. Please recall CenterPoint will be doing their own restoration due to the gas main and service replacement. Those areas began and are noted by the light brown colored erosion blanket.

  • Construction Update

    22 days ago

    The week of August 5th.

    Paiute /Drive/Pass and Sally Lane - Visu Sewer will be lining the sanitary sewer via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

    Shawnee Circle and Overholt Pass - Monday August 5th crews will preparing to install asphalt driveway ends. Installation of the asphalt is scheduled for Tuesday and Wednesday....

    The week of August 5th.

    Paiute /Drive/Pass and Sally Lane - Visu Sewer will be lining the sanitary sewer via access through manholes in the street. Avoid running your washing machine or shower during this work or you risk your sewer backing up. Please look for a notice on your front door which will contain detailed information on the process, and approximate length of time your sewer service will be unavailable for use.

    Shawnee Circle and Overholt Pass - Monday August 5th crews will preparing to install asphalt driveway ends. Installation of the asphalt is scheduled for Tuesday and Wednesday. Driveways may be driven on 1- 2 hours after they are installed, rolled and compacted. Please note that the contractor may ask you to park on the street while this driveway work occurs. Additionally, the contractor has tentatively scheduled the final layer of asphalt to be installed on Monday, August 12th. Please check back for updates.

    Bello Drive - The contractor has tentatively scheduled the final layer of asphalt to be installed on Monday, August 12th. Please check back for updates.

    Please let me know if you have any unresolved landscaping or irrigation issues at dtorgerson@EdinaMN.gov

  • Paving Update - Comanche Ct, Paiute Circle/Drive/Pass, and Sally Lane

    24 days ago

    The contractor notified the City that paving of the final layer of asphalt on Comanche Court, Paiute Circle, Paiute Drive, Paiute Pass, and Sally Lane will occur tomorrow August 1st.

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. Do not drive on the shiny black oiled surface as...

    The contractor notified the City that paving of the final layer of asphalt on Comanche Court, Paiute Circle, Paiute Drive, Paiute Pass, and Sally Lane will occur tomorrow August 1st.

    Asphalt Paving - Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. Crews will work to maintain an open lane for traffic during paving. Do not drive on the shiny black oiled surface as this will stick to car tires and can track onto driveways. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

  • Construction Update

    29 days ago

    Saturday & the week of July 29th

    Shawnee Circle & Overholt Pass – Notices have been left at front doors regarding concrete curb and driveway apron work scheduled for Monday, July 29th. Please see notice for parking information during and after concrete work.

    Concrete Installation - Wherever concrete driveway aprons or surfaces are poured, please do not drive across it for five days. The concrete needs this time to gain sufficient strength. During the time you cannot access your driveway, the Police Department will allow you to park in the street overnight in front of your home. Once the concrete...

    Saturday & the week of July 29th

    Shawnee Circle & Overholt Pass – Notices have been left at front doors regarding concrete curb and driveway apron work scheduled for Monday, July 29th. Please see notice for parking information during and after concrete work.

    Concrete Installation - Wherever concrete driveway aprons or surfaces are poured, please do not drive across it for five days. The concrete needs this time to gain sufficient strength. During the time you cannot access your driveway, the Police Department will allow you to park in the street overnight in front of your home. Once the concrete curb gains sufficient strength, a temporary gravel ramp will be built across the apron so you can access your driveway. Please read the contractor notices closely for appropriate parking locations to maintain minimum driving lanes for emergency vehicles.

    Bello Drive, Comanche Court, Paiute Circle/Drive/Pass & Sally Lane – Saturday crews will be removing portions of cracked curb and patching some areas of asphalt. Monday July 29th crews will replace the cracked curb. Turf restoration has begun in areas disturbed by roadwork. The turf contractor will be watering these areas to establish growth.The portions of yard still filled with sand will be restored with seed by CenterPoint Energy.

    If you are still owed plants or irrigation repairs due to construction please email me at dtorgerson@EdinaMN.gov.


  • Construction Update

    about 1 month ago

    Saturday & the week of July 22nd

    Shawnee Circle & Overholt Pass – Saturday July 20th the contractor will be paving the patch on Dakota Trail. Dakota trail, Overholt Pass and Shawnee Circle will remain open during this work but there may be short delays during the work. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Bello Drive, Comanche Court, Paiute Circle/Drive/Pass & Sally Lane – The landscaping contractor will begin work restoring disturbed landscape areas next week. If construction damaged your plants please email me the quantity and type of...

    Saturday & the week of July 22nd

    Shawnee Circle & Overholt Pass – Saturday July 20th the contractor will be paving the patch on Dakota Trail. Dakota trail, Overholt Pass and Shawnee Circle will remain open during this work but there may be short delays during the work. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt.

    Bello Drive, Comanche Court, Paiute Circle/Drive/Pass & Sally Lane – The landscaping contractor will begin work restoring disturbed landscape areas next week. If construction damaged your plants please email me the quantity and type of plants at dtorgerson@EdinaMN.gov.


  • Construction Update

    about 1 month ago

    Saturday & the week of July 15th

    Shawnee Circle & Overholt Pass – Saturday July 13th the contractor will be paving the first layer of asphalt. Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt. If you anticipate you will need your vehicle during this work you...

    Saturday & the week of July 15th

    Shawnee Circle & Overholt Pass – Saturday July 13th the contractor will be paving the first layer of asphalt. Please have all vehicles off the street by 7 am prior to contractor paving operations. Residents will have access to driveways during most of this work, although access may be temporarily blocked for 20-30 minutes while crews are paving directly in front of your house. The roadway may be driven on as soon as crews have placed, rolled and compacted the asphalt. If you anticipate you will need your vehicle during this work you may park on Dakota Trail but are not required to do so.

    Bello Drive, Comanche Court, Paiute Circle/Drive/Pass & Sally Lane – The turf establishment contractor has been approved to start placing topsoil. The start date is to be determined, but we anticipate their work beginning soon.



  • Construction Update

    about 2 months ago
    Flag photo

    July 4th and the week of July 8th

    Any after work non-emergency construction issues please call 952-826-1600.

    The contractor will not be working July 4th through July 7th.

    Comanche Court, Paiute Circle/Drive/Pass, Sally Lane - Next week the contractor will continue preparing the boulevard areas for topsoil.

    Bello Drive – The contractor has scheduled the paver driveway subcontractor to restore driveways during the week of July 8th.

    Shawnee Circle and Overholt Pass - Crews will maintain the gravel street surface over the weekend following any potential rain events and erosion. Concrete curb is scheduled for next week....

    July 4th and the week of July 8th

    Any after work non-emergency construction issues please call 952-826-1600.

    The contractor will not be working July 4th through July 7th.

    Comanche Court, Paiute Circle/Drive/Pass, Sally Lane - Next week the contractor will continue preparing the boulevard areas for topsoil.

    Bello Drive – The contractor has scheduled the paver driveway subcontractor to restore driveways during the week of July 8th.

    Shawnee Circle and Overholt Pass - Crews will maintain the gravel street surface over the weekend following any potential rain events and erosion. Concrete curb is scheduled for next week. Please remember to check front doors regularly for construction notices.

    Have a safe and happy Independence Day!


  • Shawnee Circle & Overholt Pass Concrete Postponed

    about 2 months ago

    Due to ongoing rain in the forecast, the crew decided to postpone the concrete curb until the week of July 8th. Rock check dams have been placed on Shawnee Circle to prevent erosion. Please check back for updates regarding concrete and asphalt paving operations.

    Due to ongoing rain in the forecast, the crew decided to postpone the concrete curb until the week of July 8th. Rock check dams have been placed on Shawnee Circle to prevent erosion. Please check back for updates regarding concrete and asphalt paving operations.

  • Construction Update

    about 2 months ago

    The week of July 1st

    Dave’s Sprinkler Repair, Bituminous Roadways subcontractor, is repairing irrigation systems within landscaped areas. Please check your front door and if Dave left his business card, call him to schedule a time to make the landscaped area irrigation system repair.

    Shawnee Circle & Overholt Pass – The contractor anticipates pouring concrete curb and gutter on Monday, July 1. The first layer of asphalt is scheduled to be paved the next day on Tuesday, July 2. Please continue to check your front door for any time sensitive notices.

    Bello Drive – The contractor will be installing paver...

    The week of July 1st

    Dave’s Sprinkler Repair, Bituminous Roadways subcontractor, is repairing irrigation systems within landscaped areas. Please check your front door and if Dave left his business card, call him to schedule a time to make the landscaped area irrigation system repair.

    Shawnee Circle & Overholt Pass – The contractor anticipates pouring concrete curb and gutter on Monday, July 1. The first layer of asphalt is scheduled to be paved the next day on Tuesday, July 2. Please continue to check your front door for any time sensitive notices.

    Bello Drive – The contractor will be installing paver driveway tie-ins.

    Comanche Court, Paiute Circle/Drive/Pass & Sally Lane – The contractor will continue preparing the boulevard areas for topsoil.

    Concrete Installation – After concrete curb or driveway aprons are poured, please do not drive across it for five days. The concrete needs this time to gain sufficient strength. During the time you cannot access your driveway, the Police Department will allow you to park in the street overnight in front of your home. Once the concrete curb gains sufficient strength, a temporary gravel ramp will be built across the apron so you can access your driveway. Please read the contractor notices left on front doors closely for appropriate parking locations to maintain minimum driving lanes for emergency vehicles.