Asphalt Paving

3 months ago

During the week of September 16th crews completed most of the concrete work in the project area. The north end of Brookside Terrace is still on hold until CenterPoint Energy can relocate two shallow gas services, which is scheduled for the week of September 23rd.

The first layer of asphalt pavement is tentatively scheduled for September 25th along Motor Street and the portion of Brookside Terrace with curb and gutter.