Todd Park E Neighborhood Roadway Reconstruction

Todd Park E Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes paving the existing gravel roadway, full installation of concrete curb and gutter and improvements to the watermain, sanitary sewer and storm sewer systems.


Todd Park E Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project includes paving the existing gravel roadway, full installation of concrete curb and gutter and improvements to the watermain, sanitary sewer and storm sewer systems.


  • Minnehaha Creek Gravel Removal

    about 17 hours ago

    During the week of August 19th crews completed the installation of water services and fire hydrants for the project.

    During the week of August 26th crews will begin removing gravel buildup in Minnehaha Creek at the storm sewer outlet. A large excavator will remove the gravel material but leave the natural creek bed intact. Erosion and sediment control measures have been installed to contain any disturbed material within the work area.

    Following the gravel removal crews will begin replacement of the storm sewer with treatment structures that will contain sediment and prevent it from entering Minnehaha...

    During the week of August 19th crews completed the installation of water services and fire hydrants for the project.

    During the week of August 26th crews will begin removing gravel buildup in Minnehaha Creek at the storm sewer outlet. A large excavator will remove the gravel material but leave the natural creek bed intact. Erosion and sediment control measures have been installed to contain any disturbed material within the work area.

    Following the gravel removal crews will begin replacement of the storm sewer with treatment structures that will contain sediment and prevent it from entering Minnehaha Creek.

  • Watermain Installed

    8 days ago

    During the week of August 12th crews installed the new watermain and fire hydrant on Brookside Terrace north of W 44th Street and installed the new Brookside Terrace hydrants south of Motor Street.

    The week of August 19th crews will install new water services for the residents north of W 44th St that are supplied off of Brookside Terrace. A tree crew will also be onsite to remove the trees that have been marked for removal. Property owners with affected trees have been notified.

    Another road closure at Brookside Terrace and W 44th St is scheduled for Wednesday, August 21st....

    During the week of August 12th crews installed the new watermain and fire hydrant on Brookside Terrace north of W 44th Street and installed the new Brookside Terrace hydrants south of Motor Street.

    The week of August 19th crews will install new water services for the residents north of W 44th St that are supplied off of Brookside Terrace. A tree crew will also be onsite to remove the trees that have been marked for removal. Property owners with affected trees have been notified.

    Another road closure at Brookside Terrace and W 44th St is scheduled for Wednesday, August 21st. Residents south of W 44th St will again exit to the south. Brookside Terrace residents north of W 44th St will have to exit to the west towards Brookside Avenue.

    The City of Edina's contractor is working closely with CenterPoint Energy to determine where their gas main is located. This is challenging because their records do not exist for this area. If you were affected by a gas outage and continue to be affected, please contact CenterPoint Energy at 1-800-752-8036.

  • Construction Kicks Off

    16 days ago

    On Friday, August 9th, crews will begin staging materials on Brookside Terrace south of W 44th Street. Crews will also begin installation of the floating silt curtain in Minnehaha Creek off of Motor Street.

    Starting on Monday, August 12th, crews will install the new watermain on Brookside Terrace north of W 44th Street. The main will be installed utilizing the horizontal directional drilling process, which involves minimal excavation, and minimal disruption to traffic and driveways.

    On Tuesday, August 13th, crews will connect the new watermain to the existing watermain in the intersection of W 44th Street,...

    On Friday, August 9th, crews will begin staging materials on Brookside Terrace south of W 44th Street. Crews will also begin installation of the floating silt curtain in Minnehaha Creek off of Motor Street.

    Starting on Monday, August 12th, crews will install the new watermain on Brookside Terrace north of W 44th Street. The main will be installed utilizing the horizontal directional drilling process, which involves minimal excavation, and minimal disruption to traffic and driveways.

    On Tuesday, August 13th, crews will connect the new watermain to the existing watermain in the intersection of W 44th Street, which will require a road closure of W 44th Street at Brookside Terrace. Brookside Terrace residents will have access to eastbound W 44th Street, but access to the west will be blocked. The contractor anticipates the road will be reopened by that evening.

    Later in the week crews will also begin excavating excess aggregate material in Minnehaha Creek off of Motor Street.

    Starting on Friday, August 9th the "No Parking" restriction for Brookside Terrace and Motor Street will be in effect, meaning parking is not allowed on either street within the project limits from the hours of 7am-9pm.

  • Project Update

    3 months ago

    Construction is tentatively scheduled to begin in either July or August. Part of the project includes replacing a storm sewer pipe from Motor Street to Minnehaha Creek and the contractor will wait until the creek elevation subsides.

    Construction is tentatively scheduled to begin in either July or August. Part of the project includes replacing a storm sewer pipe from Motor Street to Minnehaha Creek and the contractor will wait until the creek elevation subsides.

  • Project Awarded

    6 months ago

    During the March 5th meeting, City Council awarded the ENG 19-2 Chowen Park A&B and Todd Park E Neighborhood Reconstruction project to Bituminous Roadways, Inc.

    The City is working with the contractor to finalize the construction schedule for this summer. A neighborhood meeting will be scheduled in the beginning part of April to inform all residents of the schedule and address any issues or concerns residents may have.


    During the March 5th meeting, City Council awarded the ENG 19-2 Chowen Park A&B and Todd Park E Neighborhood Reconstruction project to Bituminous Roadways, Inc.

    The City is working with the contractor to finalize the construction schedule for this summer. A neighborhood meeting will be scheduled in the beginning part of April to inform all residents of the schedule and address any issues or concerns residents may have.


  • Project Updates

    6 months ago

    Hello, my name is Derek Northenscold and I am your contact for the Todd Park E neighborhood reconstruction project. I will be posting weekly updates on Better Together Edina! Feel free to "register" to join in on more conversations with the City.

    Please call or email me if you have any questions related to the project.

    I look forward to assisting and keeping you informed with this project.

    Derek


    Hello, my name is Derek Northenscold and I am your contact for the Todd Park E neighborhood reconstruction project. I will be posting weekly updates on Better Together Edina! Feel free to "register" to join in on more conversations with the City.

    Please call or email me if you have any questions related to the project.

    I look forward to assisting and keeping you informed with this project.

    Derek