Blake Road - 2022 / 2023 Roadway Reconstruction

Share Blake Road - 2022 / 2023 Roadway Reconstruction on Facebook Share Blake Road - 2022 / 2023 Roadway Reconstruction on Twitter Share Blake Road - 2022 / 2023 Roadway Reconstruction on Linkedin Email Blake Road - 2022 / 2023 Roadway Reconstruction link

Blake Road Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

The 2022 and 2023 project construction includes:

  • Complete reconstruction of the pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Partial replacement of watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems,
  • Construction of mini roundabout at the Interlachen Boulevard intersection,
  • Construction of two 5-foot on-street concrete bike lanes,
  • Construction of a 6-foot concrete sidewalk along the west side of the street south of Interlachen Boulevard, and
  • Construction of a 8-foot concrete shared use path along the west side of the street north of Interlachen Boulevard.
  • Assessments to property owners for the roadway project costs, estimated at $7,000 per residential equivalent unit.

Blake Road Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

The 2022 and 2023 project construction includes:

  • Complete reconstruction of the pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Partial replacement of watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems,
  • Construction of mini roundabout at the Interlachen Boulevard intersection,
  • Construction of two 5-foot on-street concrete bike lanes,
  • Construction of a 6-foot concrete sidewalk along the west side of the street south of Interlachen Boulevard, and
  • Construction of a 8-foot concrete shared use path along the west side of the street north of Interlachen Boulevard.
  • Assessments to property owners for the roadway project costs, estimated at $7,000 per residential equivalent unit.

  • July 11, 2024 Railing Install Update

    Share July 11, 2024 Railing Install Update on Facebook Share July 11, 2024 Railing Install Update on Twitter Share July 11, 2024 Railing Install Update on Linkedin Email July 11, 2024 Railing Install Update link

    A majority of the railing along the sidewalks and Mirror Lake within the Blake Road Street Reconstruction Project have been installed. There are a few pieces missing because they were delivered damaged. Staff is requiring the contractor to fix and re-paint those specific railing segments and install.

  • Railing Install

    Share Railing Install on Facebook Share Railing Install on Twitter Share Railing Install on Linkedin Email Railing Install link
    supporting image

    Installation of railings along the sidewalk and Mirror Lake started this week. This is exciting. It is the last major work item remaining to complete this project. There will continue to be some miscellaneous warranty work in the near term. Thanks again for the patience on this incredible project.

  • May 29 and 30, Concrete Warranty Work

    Share May 29 and 30, Concrete Warranty Work on Facebook Share May 29 and 30, Concrete Warranty Work on Twitter Share May 29 and 30, Concrete Warranty Work on Linkedin Email May 29 and 30, Concrete Warranty Work link

    The contractor will be removing and replacing broken concrete under warranty. They will be managing traffic as needed. Thanks for the patience.

  • May 2024

    Share May 2024 on Facebook Share May 2024 on Twitter Share May 2024 on Linkedin Email May 2024 link

    The contractor is working on a list of items that need to be finished or corrected before the project is complete. The railings along the sidewalk should be installed soon. Fabrication and painting of the railings is almost complete. Thanks

  • 2024 Railing and Signs

    Share 2024 Railing and Signs on Facebook Share 2024 Railing and Signs on Twitter Share 2024 Railing and Signs on Linkedin Email 2024 Railing and Signs link

    Later this week the contractor will be removing the sign mounts in the sidewalk and installing sign mounts to the walls. This removes an obstruction in the sidewalk during sidewalk snowplowing operations. The railings are being fabricated now. Railings have a very long lead time. They are tentatively scheduled for installation early June. Thanks

  • Nov. 9, 2023 Project Update

    Share Nov. 9, 2023 Project Update on Facebook Share Nov. 9, 2023 Project Update on Twitter Share Nov. 9, 2023 Project Update on Linkedin Email Nov. 9, 2023 Project Update link

    The final layer of pavement was placed this week. Pavement markings and regulatory signs are scheduled towards the end of next week. If the remaining work goes as scheduled, the road will be open before Thanksgiving and potentially the weekend before. Thanks for all the patience with this project.

  • October 13, 2023 Project Update

    Share October 13, 2023 Project Update on Facebook Share October 13, 2023 Project Update on Twitter Share October 13, 2023 Project Update on Linkedin Email October 13, 2023 Project Update link

    The area south of Mirror Lake is making great progress. The concrete curb was installed this week. The first two layers of blacktop is scheduled for next week along with concrete sidewalks. If everything goes as planned, the final layer of blacktop would occur the first week of November. Recall after the final layer of blacktop is placed, pavement markings and signs need to be installed before we can re-open the road to traffic. It is anticipated that it will re-open before Thanksgiving. The project team appreciates all the patience with the longer than expected project.

  • September 21, 2023 Project Update

    Share September 21, 2023 Project Update on Facebook Share September 21, 2023 Project Update on Twitter Share September 21, 2023 Project Update on Linkedin Email September 21, 2023 Project Update link

    As most people already know, the north half of the project is complete and open to traffic. The area south of Mirror Lake is still closed to traffic as the contractor finishes up. All underground utilities are complete, road grading is in process and concrete curb is tentatively scheduled for the first week of October. Progress also continues on the stone retaining walls. Of note is that the railings that will be placed on top of the wall near the sidewalks will be installed at a later date due to fabrication time.

  • Road Opening Update

    Share Road Opening Update on Facebook Share Road Opening Update on Twitter Share Road Opening Update on Linkedin Email Road Opening Update link

    Interlachen Boulevard is open east of Blake Road, and Blake Road is open between the land bridge and the Edina / Hopkins city limits. Blake Road continues to be closed south of the land bridge. See the map for details.

  • Water Shutoff Interlachen Boulevard - 8/16/23

    Share Water Shutoff Interlachen Boulevard - 8/16/23 on Facebook Share Water Shutoff Interlachen Boulevard - 8/16/23 on Twitter Share Water Shutoff Interlachen Boulevard - 8/16/23 on Linkedin Email Water Shutoff Interlachen Boulevard - 8/16/23 link

    Problems with the water system valves on Interlachen Boulevard require an emergency water shutoff today, 8/16. The contractor is working as quickly as possible to restore water service, but it’s anticipated that the shutdown will last until 6 PM. Affected streets include those on Interlachen Boulevard west of Blake Road.

Page last updated: 11 Jul 2024, 06:25 AM