Blake Road - 2022 Roadway Reconstruction

Share on Facebook Share on Twitter Share on Linkedin Email this link

Blake Road Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project, scheduled for construction in 2022, includes:

  • Complete reconstruction of the pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Partial replacement of watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems,
  • Construction of mini roundabout at the Interlachen Boulevard intersection,
  • Construction of two 5-foot on-street concrete bike lanes,
  • Construction of a 6-foot concrete sidewalk along the west side of the street south of Interlachen Boulevard, and
  • Construction of a 8-foot concrete shared use path along the west side of the street north of Interlachen Boulevard.
  • Assessments to property owners for the roadway project costs, estimated at $7,000 per residential equivalent unit

Blake Road Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project, scheduled for construction in 2022, includes:

  • Complete reconstruction of the pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Partial replacement of watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems,
  • Construction of mini roundabout at the Interlachen Boulevard intersection,
  • Construction of two 5-foot on-street concrete bike lanes,
  • Construction of a 6-foot concrete sidewalk along the west side of the street south of Interlachen Boulevard, and
  • Construction of a 8-foot concrete shared use path along the west side of the street north of Interlachen Boulevard.
  • Assessments to property owners for the roadway project costs, estimated at $7,000 per residential equivalent unit
  • Comcast Outages / Overnight Work Dec. 19 & 20

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Comcast Communications will be relocating existing aerial cables to new underground cables. Their contractor, D&D Service, will be using a mini excavator (minimal use), trucks with fiber splicing trailers with small generators, aerial bucket trucks and hydro excavators (minimal use). This work is scheduled to occur between midnight and 6 am on two separate evenings. Work will start at midnight on Monday, Dec. 19 until 6 am on Tuesday, Dec. 20 and again starting at midnight on Tuesday, Dec. 20 until 6 am on Wednesday, Dec. 21. There are 6 locations for this work.

    1. Intersection of Waterman Avenue and Blake Road South on the northeast corner
    2. Intersection of Interlachen Boulevard and Blake Road South on the northside of the road
    3. Southside of Interlachen Boulevard near home address 6195
    4. Northside of Interlachen Boulevard near home address 6321
    5. Intersection of Blake Road South and Oak Bend Lane on the northwest corner
    6. Westside of Blake Road South at approximate address 5124

    There will be outages to service in the area. The service outages will vary. The official cutover start and end times are 12:00 P.M. to 06:00 A.M. All service impacts must operate in these time frames. These outages are approved through corporate Comcast and follow all protocols. The goal for the fiber splicers is to bring the major service impacts back on line as soon as possible. They will be using flaggers to manage traffic.

  • Sanitary Sewer Main Lining

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Sanitary sewer lining began on 11/8 and is scheduled to conclude on 11/11. Pungent odors from the lining process are common. To prevent odors in your home, pour a gallon of water into floor drains and infrequently used sinks. Limiting major water use is required to avoid a sewer backup if you live on Blake Road north of Waterman Avenue. Check your front door daily for details and notice of this work occurring on Blake Road. Please contact Xavier Kopp with questions XKopp@wsbeng.com or 612-741-7096.

  • October 27 Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The contractor will start paving 2 of 3 layers of street pavement today. They will ramp at the edge of the concrete curb and gutter so snowplows can operate this winter. Next year, the contractor will return to complete the sidewalk along the west side, turf restoration, the final layer of street pavement, and permanent pavement markings. They were unable to completely finish this phase of the project due to private utility conflicts and concrete & labor shortages. Thanks for your patience with this project.

  • October 14 Intersection Closure Information

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The intersections at Belmore and Mendelssohn with Blake Road are closed until mid-next week due to the installation of concrete valley gutters. Spruce and Maloney are still open for access in the neighborhood. Thanks

  • Project Update October 13

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The contractor's schedule has concrete work finishing this week, backfill and prep for paving the week of Oct. 17, paving the two of three layers of the asphalt street the week of Oct. 24, and paving the final layer the week of Oct. 31 or Nov. 7. If schedules and weather continue to align, the road should be open the 2nd or 3rd week of November. Thanks for you patience.

  • Project Update October 10

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The unground utilities are complete. The team is conducting watermain testing before getting residents back on the permanent water system and off the temporary water system. That work should occur this week. The grading of the street for new concrete curb and gutter and street pavement should be complete this week. Installing concrete curb and gutter is the next step in the reconstruction process. The contractor is trying to confirm concrete availability but with the concrete shortage, timelines are hard to define. Most likely the concrete sidewalk will not be installed this year due to a lack of concrete. Thanks for your patience.

  • Project Update September 30

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The contractor will be wrapping up installing new underground utility pipes for the water and storm sewer systems by mid-October while at the same time completing roadway grading operations.

    All contractors in the Twin Cities have been notified of a concrete shortage by concrete suppliers. City and contractor staff are gathering more information to determine how that may impact this project. The contractor hopes to install concrete curb during the week of Oct. 17 but that is contingent on the concrete supply issue.

  • Project Update September 22

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The contractor is making great progress installing new underground utility pipes for the water and storm sewer systems. We understand the concerns of residents east of Blake Rd trying to leave their neighborhood or walk their kids to the bus stop west of Blake Rd. The contractor installed signs to provide safer, marked crossings for residents to walk across Blake Rd. Continue to contact the project team if you see things that concern you. Thanks

  • Project Update September 9

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The private utilities are nearly clear of the site. The city contractor will be starting replacement of the watermain system next week. This will require some short-term water shut-offs. Please check your front doors for flyers with details. Watermain work is scheduled to last 2-weeks followed but underground storm sewer installation. Please continue to be careful when traveling to and from your house. Thanks

  • Blake Road Closure and Reconstruction Begin August 15

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Blake Road will be closed between Waterman Avenue and Spruce Road for roadway and utility improvements by S.M. Hentges & Sons beginning on Monday August 15 until November 2022. The detour route will be Interlachen Boulevard, Highway 100 and Excelsior Boulevard. Residents east of Blake Road with no outlet other than Blake Road should enter and exit as shown on the following map.

    The contractor will begin by reclaiming the asphalt pavement, which is the process of grinding the existing pavement into a gravel base. Removal of driveway ends within the construction limits will begin as necessary in preparation for the underground utility work. After the removals are complete, crews will begin installing a temporary above ground watermain in advance of the watermain work.

    We invite you to review this document summarizing what to expect during construction.