2023 Construction Update - March 3

The Blake Road Project is resuming construction operations. Work will start on Monday, March 13. The 2023 work will be phased. Phase 1 is located from Waterman Avenue to along Interlachen Boulevard just west of the Interlachen Country Club driveway. This phase includes the land bridge across Mirror Lake and the roundabout. Phase 2 is Blake Road south of the land bridge to Scriver Road. There will be tree removals, dust, mud, equipment noise, and noise associated with sheet pile installation. Vibration monitoring will start with construction operations. Working hours are 7 am to 9 pm. Access for residents will be provided. Also note there is some work from last year to finish between Spruce Road and Waterman Avenue. Scheduled construction operations are the following.

Week of March 6: Advanced road closure notifications and detour signage. Delivery of equipment.

Week of March 13: Clear and grub trees for Phases 1 and 2 and start removals

Week of March 20: Begin sheet pile installation along Mirror Lake in Phase 1


Share 2023 Construction Update - March 3 on Facebook Share 2023 Construction Update - March 3 on Twitter Share 2023 Construction Update - March 3 on Linkedin Email 2023 Construction Update - March 3 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>