October 13, 2023 Project Update

The area south of Mirror Lake is making great progress. The concrete curb was installed this week. The first two layers of blacktop is scheduled for next week along with concrete sidewalks. If everything goes as planned, the final layer of blacktop would occur the first week of November. Recall after the final layer of blacktop is placed, pavement markings and signs need to be installed before we can re-open the road to traffic. It is anticipated that it will re-open before Thanksgiving. The project team appreciates all the patience with the longer than expected project.