Project Update October 10

The unground utilities are complete. The team is conducting watermain testing before getting residents back on the permanent water system and off the temporary water system. That work should occur this week. The grading of the street for new concrete curb and gutter and street pavement should be complete this week. Installing concrete curb and gutter is the next step in the reconstruction process. The contractor is trying to confirm concrete availability but with the concrete shortage, timelines are hard to define. Most likely the concrete sidewalk will not be installed this year due to a lack of concrete. Thanks for your patience.

Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>