Project Update October 13

The contractor's schedule has concrete work finishing this week, backfill and prep for paving the week of Oct. 17, paving the two of three layers of the asphalt street the week of Oct. 24, and paving the final layer the week of Oct. 31 or Nov. 7. If schedules and weather continue to align, the road should be open the 2nd or 3rd week of November. Thanks for you patience.