Project Update September 30
The contractor will be wrapping up installing new underground utility pipes for the water and storm sewer systems by mid-October while at the same time completing roadway grading operations.
All contractors in the Twin Cities have been notified of a concrete shortage by concrete suppliers. City and contractor staff are gathering more information to determine how that may impact this project. The contractor hopes to install concrete curb during the week of Oct. 17 but that is contingent on the concrete supply issue.
Share Project Update September 30 on Facebook
Share Project Update September 30 on Twitter
Share Project Update September 30 on Linkedin
Email Project Update September 30 link
