September 21, 2023 Project Update
As most people already know, the north half of the project is complete and open to traffic. The area south of Mirror Lake is still closed to traffic as the contractor finishes up. All underground utilities are complete, road grading is in process and concrete curb is tentatively scheduled for the first week of October. Progress also continues on the stone retaining walls. Of note is that the railings that will be placed on top of the wall near the sidewalks will be installed at a later date due to fabrication time.