December 21 2021

City Council Authorizes Design and Contractor Bidding

April 11 2022

CenterPoint Energy Gas Main Replacement Begins

April 19 2022

City Council Awards Construction Contract

May 31 2022

City's Contractor Begins Construction

December 13 2021

Public Hearing Opens - City Council meets to consider authorizing project design

December 15 2021

Public Hearing Comment Period Closes at noon

December 21 2021

City Council meets to consider authorizing project design - Final Decision