August 1 Project Update

We reported challenges to the installation of two retaining walls along the north side of 50th Street. The soils were different then the soil borings indicated. The contractor and engineers have determined a H-pile wall should work. Final analysis is being done now with installation occurring shortly after. This operation will be loud. As soon as a schedule is known, we will update the BetterTogetherEdina website. The contractor was able to install a majority of the concrete curb and gutter this week. Median concrete and sidewalks are also occurring. Opening the new street to traffic as soon as safe continues to be a priority.