50th Street and Grange Rd Improvements

Share 50th Street and Grange Rd Improvements on Facebook Share 50th Street and Grange Rd Improvements on Twitter Share 50th Street and Grange Rd Improvements on Linkedin Email 50th Street and Grange Rd Improvements link

The City Council approval of a development proposal at 4917 Eden Avenue has provided an opportunity for improvements to the transportation system near City Hall. Phase 2 of those improvements is tentatively scheduled for construction in 2024. The overview graphic shows the concept along 50th Street and Grange Rd.

The City Council approval of a development proposal at 4917 Eden Avenue has provided an opportunity for improvements to the transportation system near City Hall. Phase 2 of those improvements is tentatively scheduled for construction in 2024. The overview graphic shows the concept along 50th Street and Grange Rd.

  • July 24 Pile Driving Update

    Share July 24 Pile Driving Update on Facebook Share July 24 Pile Driving Update on Twitter Share July 24 Pile Driving Update on Linkedin Email July 24 Pile Driving Update link

    The installation of two sheet pile walls did not go according to plan. The soils were different then the soil borings indicated. Staff is working with the structural engineers and the contractor to determine a new plan. After a new plan is determined, we will update the project schedule. We understand the importance of opening 50th Street to traffic as soon as it is safe to do so. Thanks for the understanding.

  • July 22 Pile Driving Update

    Share July 22 Pile Driving Update on Facebook Share July 22 Pile Driving Update on Twitter Share July 22 Pile Driving Update on Linkedin Email July 22 Pile Driving Update link

    Pile driving operations have hit unexpected materials and have been suspended at this time. The project team is assessing how to build the required walls. Thanks

  • July 18 Pile Driving Update

    Share July 18 Pile Driving Update on Facebook Share July 18 Pile Driving Update on Twitter Share July 18 Pile Driving Update on Linkedin Email July 18 Pile Driving Update link

    The contractor anticipates starting pile driving operations on Friday, July 19. It is scheduled for Friday, Saturday this week and Monday – Wednesday next week if things go well. This will be loud and disruptive work. Thanks

  • July 11 Update

    Share July 11 Update on Facebook Share July 11 Update on Twitter Share July 11 Update on Linkedin Email July 11 Update link

    The 50th Street and Grange Road Street Reconstruction Project is progressing nicely. Underground watermain, storm sewer and sanitary sewer improvements are wrapping up now. Street grading operations are scheduled to start the week of July 15. Also note that tentatively starting on July 18 – July 25, piling driving work will start. A large crane will be driving large steel plates into the slope behind existing traffic signal at 50th and Grange to create space for the new sidewalks and new traffic signal. This work is anticipated to last 5 days. This work is loud and will occur during normal business hours. There will also be another large crane in front of City Hall to start a re-roofing and solar panel installation on the roof of City Hall. Thanks for the continued patience.

  • July 2 Update

    Share July 2 Update on Facebook Share July 2 Update on Twitter Share July 2 Update on Linkedin Email July 2 Update link

    The contractor is tentatively scheduled to finish all watermain work this week. They do not anticipate working July 5 or July 6. We are coordinating access to the Sunnyslope Neighborhood during the 4th of July parade. During the week of July 8, the contractor will start storm sewer upgrades. Thanks.

  • June 21 Construction Update

    Share June 21 Construction Update on Facebook Share June 21 Construction Update on Twitter Share June 21 Construction Update on Linkedin Email June 21 Construction Update link

    Precipitation in Edina for May and early June has been well above normal. This has been a good thing related to the last two years of drought conditions but it is impacting street reconstruction projects. It has been too wet to complete any work on 50th Street & Grange Road during the week of June 17. Watermain was scheduled for the week of June 17. That work has been pushed to the week of June 24. Its nearly impossible to dig trenches 7-8-ft deep to replace watermain or other underground pipes when its raining this much. We continue to hope for some dry weather to keep this project on schedule. Thanks for the patience.

  • Road Closure Started - June 10

    Share Road Closure Started - June 10 on Facebook Share Road Closure Started - June 10 on Twitter Share Road Closure Started - June 10 on Linkedin Email Road Closure Started - June 10 link

    Thanks for the notes, emails and phone calls. Monday was the first day of the closure and adjustments to signage to better inform the public are happening. The first week of any road closure is the worst. The project will take most of the summer to complete. It is updating underground water, sanitary sewer, and storm sewer pipes, installing wide sidewalks, medians and a new traffic signal. These surface improvements will improve the safety for all users. Sorry for the inconvenience.

  • Construction Start June 10, 2024

    Share Construction Start June 10, 2024 on Facebook Share Construction Start June 10, 2024 on Twitter Share Construction Start June 10, 2024 on Linkedin Email Construction Start June 10, 2024 link

    The 50th Street and Grange Road Street Reconstruction Project is scheduled to start June 10. The project limits from Grange Rd from 50th St to the City Hall west entrance and 50th St from Grange Rd to just east of Dale Dr. 50th St and Grange Rd will be closed to traffic. Eden Avenue will be open to traffic. The northbound off-ramp and northbound on-ramp on Grange will be open during much of the project. Westbound 50th St will be detoured north at France Ave to Excelsior Blvd to Highway 100. Thanks

  • Private Utility Work - April / May

    Share Private Utility Work - April / May on Facebook Share Private Utility Work - April / May on Twitter Share Private Utility Work - April / May on Linkedin Email Private Utility Work - April / May link

    The project requires adjustments to some of the private utilities such as power poles and related underground utilities. The private utility companies will be starting this work soon. The work will occur in April and May before the contractor starts major work. Look for lane shifts in the area. Road closures should not be needed until the city project starts this summer. Thanks

  • Contractor Selected / Detour Maps

    Share Contractor Selected / Detour Maps on Facebook Share Contractor Selected / Detour Maps on Twitter Share Contractor Selected / Detour Maps on Linkedin Email Contractor Selected / Detour Maps link
    supporting image

    We recently opened bids on the project along 50th Street and Grange Road for construction summer 2024. We received very competitive pricing. S.M. Hentges was the low bidder. This contractor also completed the roundabouts at Eden and Arcadia & both at Eden and Grange over the past few years. We will soon be meeting with them to develop a project schedule. The project is scheduled for construction during the summer months. A more formal schedule will be shared when available. There will be a local detour and a project detour. These maps are in the documents area of this website. Thanks, Chad Millner, City Engineer.

Page last updated: 24 Jul 2024, 05:39 AM