September 18 Update - Road Opening Soon
The contractor continues to make progress. The wiring for the traffic signal and the new traffic signal should be completed early during the week of September 23. The final layer of paving is scheduled early in that same week. The contractor will be cleaning the site in anticipation of the Police Department's Open House on Thursday, September 26 from 5 - 7 pm. Come check out the open house and the new street. After the police event, the contractor will install street signs and pavement markings and open the street. We anticipate opening the street early during the week of September 30. Thanks for your patience with this project.