Eden Ave Construction Update: April 28, 2022

With the drier weather, underground utility work is accelerating on Eden Ave and the contractor is making good progress. Pavement removals are complete and sanitary sewer construction between Arcadia Ave and the Our Lady of Grace driveway is underway. Once sanitary sewer work has advanced to the driveway, the contractor will construct new water main and storm sewer within the same segment.

Pending weather, the contractor is hoping to be complete with all three new utilities through the driveway by approximately Friday, May 6th. This means that beginning on approximately Monday, May 9th, Eden Ave will be closed to traffic between the railroad bridge and the recently-installed temporary driveway to Our Lady of Grace. Eastbound traffic will be detoured via the route shown in the attached map and signs will be in place for Our Lady of Grace traffic. Westbound thru traffic will continue to be detoured via the currently in-place route on 50th St and Vernon Ave.

Additional information will be provided as the contractor’s schedule becomes clearer.

Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>