Eden, Arcadia, and Brookside Avenues Street Reconstruction

Share on Facebook Share on Twitter Share on Linkedin Email this link

The project would include the reconstruction of Eden Avenue from Grandview Square to Highway 100 including a roundabout at Arcadia Ave, replacement of existing concrete curb and gutter except adjacent to the Avidor, installation of new concrete curb and gutter, construction of new concrete sidewalks on the north side except adjacent to the Avidor and a shared-use path on the south side. It also includes improvement to the sanitary sewer, watermain, storm sewer, and street lighting systems. Street improvements will also be completed along Brookside Avenue from Eden Avenue to the Grandview Parking Ramp. These include concrete curb and gutter, utility improvements, street lighting, and bituminous paving.

The project is scheduled for two phases over 2021 and 2022. The west half from Grandview Square to approximately Brookside Ave will be constructed in 2021. The east half from Brookside Avenue to Highway 100 will be constructed in 2022.

The project would include the reconstruction of Eden Avenue from Grandview Square to Highway 100 including a roundabout at Arcadia Ave, replacement of existing concrete curb and gutter except adjacent to the Avidor, installation of new concrete curb and gutter, construction of new concrete sidewalks on the north side except adjacent to the Avidor and a shared-use path on the south side. It also includes improvement to the sanitary sewer, watermain, storm sewer, and street lighting systems. Street improvements will also be completed along Brookside Avenue from Eden Avenue to the Grandview Parking Ramp. These include concrete curb and gutter, utility improvements, street lighting, and bituminous paving.

The project is scheduled for two phases over 2021 and 2022. The west half from Grandview Square to approximately Brookside Ave will be constructed in 2021. The east half from Brookside Avenue to Highway 100 will be constructed in 2022.

  • Eden Avenue Detour

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Eden Ave is closed until the end of October for roadway and utility reconstruction. Grandview businesses remain open during construction. Follow the posted detour routes. We’re sorry for the inconvenience.

    We apologize for this lengthy inconvenience and thank you for your patience during these much needed improvements.

  • Construction Starting Tuesday, August 3

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Beginning on Tuesday, August 3, Eden Ave will be closed to through traffic between Grandview Square and the railroad bridge. A detour to Vernon Ave/50th St will be in place. Access for local traffic to individual driveways (as well as Brookside Ave) will be maintained. In an effort to limit traffic through the construction area, please notify tenants, customers, and employees of this closure and urge them to seek alternate routes as well (if available).

    Work expected to begin next week includes the placement of traffic control devices and detour signage, the installation of the temporary water main system, and the removal of Phase 1 (from Grandview Square to the railroad) pavement, curb and gutter, sidewalk, and trees.

    In addition, a brief shutdown to the water main is expected next week to facilitate the installation of the temporary water main. Businesses that will be impacted by this shutdown will be notified at least 24 hours in advance. Once the temporary water main is in place, work on the new water main will begin.

    Phase 1 is expected to be completed later this fall. Work on Phase 2 (from the railroad to TH 100) will begin next spring.

Page last updated: 10 August 2021, 14:17