Eden Ave Construction Update: July 18

City staff continues to meet with the contractor to discuss schedules. Recall the project experienced a last minute, unknown electric power conflict. The utility company has been working on a relocation but due to staffing, workload and storm issues in the Midwest, they have only been onsite on a part time basis. The issue will be addressed soon but it has not confirmed yet that the old power line is dead. Until confirmation is received that it is safe to work, the project is on hold. Unfortunately, due to this conflict, the project lost 4-5 weeks of production time. This pushes the completion date to early to mid-October. This was not our original plan and the project team is sorry.