Eden Ave Construction Update: May 4, 2022

The public utilities through the Our Lady of Grace driveway are expected to be complete tomorrow (May 5). The Contractor plans to change traffic control such that access to Our Lady of Grace (via the permanent driveway location) will be from the east only. This change will occur tomorrow evening after school pick-up has been completed. Traffic from the west will be detoured via Vernon Ave and Arcadia Ave and signage for Our Lady of Grace will be in place. This means that beginning Friday morning (May 6), all access to Our Lady of Grace via Eden Ave will be from the east as it was earlier this spring. Refer to the attached detour map.