Eden Avenue Construction Update: September 8

Weather permitting, all concrete work on the project (except underneath the railroad bridge) will be completed by end of day tomorrow. We continue to work with railroad representatives to get the required agreements in place to complete that work. Because the schedule for receiving those agreements is unknown, the work underneath the railroad bridge could be delayed until next year. Regardless of when this work takes place, it will be completed without closing the road to traffic.

Next week, the Contractor is planning to begin placing topsoil, installing signs, and placing seed. Once complete, the Contractor will be able to pave the final layer of asphalt, which is tentatively scheduled for the week of September 19. The pavement must cool sufficiently before pavement markings may be placed (typically several days) so expect that work to take place the week of September 26.

Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>