Sanitary Pipe Lining - Week of March 28

Sanitary sewer lining is scheduled to begin next week. The map shows the specific locations where the lining will be taking place. This will generally consist of a truck parked at a manhole with no excavation being required. Through traffic and business access will generally be unaffected by this work with only short term lane closures being required.

In an effect to reduce impacts to businesses, all lining is proposed to take place during overnight hours, except for the segment scheduled for Friday, March 25th, which will take place during daytime hours. Crews will be on site for night work between approximately 7 PM and 7 AM, with lining beginning at about 8 PM.