April 2025 Construction Update

Interior work is in full swing! The interior wall framing is nearly complete and rough ins for Electrical and Plumbing systems has started on the upper floors, drywall work will follow shortly with an expected completion in late April or early May.

The warmer weather and lack of snow cover allowed early access to the geo-thermal well field on the south end of the site and the exterior stonework is nearing completion on all four sides of the building.

The project remains on budget and on schedule. Watch the most recent drone flyover video of the new Fire Station 2.