April 2025 Construction Update
Interior work is in full swing! The interior wall framing is nearly complete and rough ins for Electrical and Plumbing systems has started on the upper floors, drywall work will follow shortly with an expected completion in late April or early May.
The warmer weather and lack of snow cover allowed early access to the geo-thermal well field on the south end of the site and the exterior stonework is nearing completion on all four sides of the building.
The project remains on budget and on schedule. Watch the most recent drone flyover video of the new Fire Station 2.
Share April 2025 Construction Update on Facebook
Share April 2025 Construction Update on Twitter
Share April 2025 Construction Update on Linkedin
Email April 2025 Construction Update link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends