June 2025 Construction Update

Interior work continues! Finishes that include painting, tile and flooring are nearing completion inside the office spaces and living quarters. The electrical and plumbing systems are starting to come online, and the building should reach the milestone of being connected to permanent power by the end of June.

On the exterior the concrete and asphalt roadways will have the base courses completed by July 4th and the permeable paver sections and underlying stormwater retention systems that make up the bulk of the roads and driveways are underway.

You can see the flyover video below that the rooftop solar system has been installed and will be connected to the electrical grid once the building is operational.

Drone Update - Edina Fire Station

The project remains on budget and on schedule.

Share June 2025 Construction Update on Facebook Share June 2025 Construction Update on Twitter Share June 2025 Construction Update on Linkedin Email June 2025 Construction Update link