Construction Update - 11/3/2023

Phase 2: Monterey Ave and Lynn Ave

  • Topsoil installation will continue the week of 11/6, along with dormant seeding. The dormant seed will be evaluated in the spring for effectiveness.


Phase 3: Kipling Ave and W 40th St

  • Asphalt driveway restoration is complete.
  • Topsoil installation will continue the week of 11/6, along with dormant seeding. The dormant seed will be evaluated in the spring for effectiveness.


Project Wide

  • The final asphalt layer is scheduled for mid-week the week of 11/6.
    • Check your front door for parking and driveway access.
    • The asphalt can be driven on following final compaction rolling.
  • Irrigation repairs have been suspended for the winter. If your irrigation system was not repaired, reach out to Nina for the next steps.
  • Landscape plantings and trees have been suspended until next spring. If you have not already done so, please reach out to Nina with any landscaping items remaining to be installed/delivered to your property in the spring.


Share Construction Update - 11/3/2023 on Facebook Share Construction Update - 11/3/2023 on Twitter Share Construction Update - 11/3/2023 on Linkedin Email Construction Update - 11/3/2023 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>