Construction Update - 11/3/2023
Phase 2: Monterey Ave and Lynn Ave
- Topsoil installation will continue the week of 11/6, along with dormant seeding. The dormant seed will be evaluated in the spring for effectiveness.
Phase 3: Kipling Ave and W 40th St
- Asphalt driveway restoration is complete.
- Topsoil installation will continue the week of 11/6, along with dormant seeding. The dormant seed will be evaluated in the spring for effectiveness.
Project Wide
- The final asphalt layer is scheduled for mid-week the week of 11/6.
- Check your front door for parking and driveway access.
- The asphalt can be driven on following final compaction rolling.
- Irrigation repairs have been suspended for the winter. If your irrigation system was not repaired, reach out to Nina for the next steps.
- Landscape plantings and trees have been suspended until next spring. If you have not already done so, please reach out to Nina with any landscaping items remaining to be installed/delivered to your property in the spring.