Morningside C Neighborhood Roadway Reconstruction

Share Morningside C Neighborhood Roadway Reconstruction on Facebook Share Morningside C Neighborhood Roadway Reconstruction on Twitter Share Morningside C Neighborhood Roadway Reconstruction on Linkedin Email Morningside C Neighborhood Roadway Reconstruction link

Morningside C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project is scheduled for construction in 2023. The work typically includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter is anticipated,
  • Complete replacement of watermain and water services is anticipated,
  • Replacement of fire hydrants and watermain gate valves,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Construction of concrete sidewalks along Kipling Avenue (west side), Monterey Avenue (west side), Inglewood Avenue (south / east side), West 40th Street (south side) as well as Lynn Avenue (east side) and Grimes Avenue where gaps in the sidewalk network exist on the east side.
  • A preliminary assessment amount of $13,800 per Residential Equivalent Unit was approved by the Council at the December 2022 public hearing. This $13,800 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties. Favorable bids were received. If unforeseen changes do not occur during construction, an assessment cost savings of up to 30% could occur.

Morningside C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project is scheduled for construction in 2023. The work typically includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter is anticipated,
  • Complete replacement of watermain and water services is anticipated,
  • Replacement of fire hydrants and watermain gate valves,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Construction of concrete sidewalks along Kipling Avenue (west side), Monterey Avenue (west side), Inglewood Avenue (south / east side), West 40th Street (south side) as well as Lynn Avenue (east side) and Grimes Avenue where gaps in the sidewalk network exist on the east side.
  • A preliminary assessment amount of $13,800 per Residential Equivalent Unit was approved by the Council at the December 2022 public hearing. This $13,800 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties. Favorable bids were received. If unforeseen changes do not occur during construction, an assessment cost savings of up to 30% could occur.
  • Turf Restoration Update - 7/9/2024

    Share Turf Restoration Update - 7/9/2024 on Facebook Share Turf Restoration Update - 7/9/2024 on Twitter Share Turf Restoration Update - 7/9/2024 on Linkedin Email Turf Restoration Update - 7/9/2024 link

    Turf Restoration work is scheduled to begin as soon as 7/9, weather permitting. One or two of the following three methods will occur at your property depending upon the current condition of the turf.


    • Brillion seeding. A small tractor pulls a machine behind it that drops seed onto the turf, the seed is then pushed into the ground by a metal disc.
    • Slit seeding. Like brillion seeding, but is a smaller machine, typically self-propelled.
    • Hand raking. Smaller areas will have the soil scarified by raking, seed will then be distributed of the area and the area will be raked again.


    Following any of the methods listed above, hydromulch and fertilizer will be applied to the restored areas. The hydromulch will help keep the seed and soil moist and prevent erosion and seed loss.

    The City will continue working with the contractor this summer to ensure the City’s specifications are met, including proper turf growth without significant weeds. Thank you for your patience as we navigate the extremely wet start to the spring and summer.

  • Turf Establishment - Weeds

    Share Turf Establishment - Weeds on Facebook Share Turf Establishment - Weeds on Twitter Share Turf Establishment - Weeds on Linkedin Email Turf Establishment - Weeds link

    A licensed contractor will begin applying herbicide to resolve weed issues in the City right of way in front of your home. This work is scheduled to occur soon after on Wednesday, 6/26. Please remain off the treated area for 48 hours and do not water the treated area for 48 hours.

    City staff will continue to review the project area after the herbicide application and if necessary, additional seeding. The City will continue working with the contractor to ensure the City’s specifications are met, including proper turf growth without significant weeds.

  • Turf Restoration Update – 6/25/24

    Share Turf Restoration Update – 6/25/24 on Facebook Share Turf Restoration Update – 6/25/24 on Twitter Share Turf Restoration Update – 6/25/24 on Linkedin Email Turf Restoration Update – 6/25/24 link

    Turf Restoration work is scheduled to begin as soon as 6/26, weather permitting, including:

    • If necessary, topsoil will be added to fill in low spots.
    • Seeding and hydromulch
    • Watering
    • Tips for growing green grass can be found here.

    The City will continue working with the contractor this summer to ensure the City’s specifications are met, including proper turf growth without significant weeds.

    As necessary following turf restoration, herbicide may be applied to resolve weed issues in the City right of way in front of your home.

    Thank you for your patience as we navigate the extremely wet start to the spring and summer.

  • Sanitary Sewer Main Lining

    Share Sanitary Sewer Main Lining on Facebook Share Sanitary Sewer Main Lining on Twitter Share Sanitary Sewer Main Lining on Linkedin Email Sanitary Sewer Main Lining link
    supporting image

    The contractor began installing a structural liner in the sanitary sewer main. This work will is scheduled to conclude by 6/21.

    • The contractor will notify you in advance to coordinate the work if it impacts you by hanging a notice on your door.
      • Please check your door frequently.
    • This notice will contain detailed information on the process, and the approximate length of time your sewer service will be unavailable for use.
      • Don’t take a shower or run a load of laundry during this or your sewer will back up.
    • You can minimize the possibility of odors migrating into your home by pouring a gallon of water into floor and laundry drains and infrequently used sinks.
  • Spring Work Resumes

    Share Spring Work Resumes on Facebook Share Spring Work Resumes on Twitter Share Spring Work Resumes on Linkedin Email Spring Work Resumes link

    The Contractor resumed work in May and is scheduled to conclude by the end of June.

    • Landscaping replacement began
    • Tree replacement began
    • Irrigation repairs began
    • Turf Restoration work is scheduled to begin soon.
      • If necessary, topsoil will be added to fill in low spots.
      • Seeding and hydromulch
      • Watering
      • Tips for growing green grass can be found here.

    Turf restoration was scheduled to begin the week of 5/20, but the location where the contractor purchases topsoil is exposed to weather and is wet from rain. Topsoil needs to be loose and friable during placement. Otherwise, it clumps together and increases the risk of over compaction, minimizing the seed’s ability to properly germinate. Thank you for your patience.

  • Nina Bonanno - Updated Contact Info

    Share Nina Bonanno - Updated Contact Info on Facebook Share Nina Bonanno - Updated Contact Info on Twitter Share Nina Bonanno - Updated Contact Info on Linkedin Email Nina Bonanno - Updated Contact Info link

    Updated contact info for Nina Bonanno, onsite project manager, can be found here. Stay tuned for updates on:

    • Remaining Irrigation repairs
    • Topsoil regrading, seeding and hydromulch touch ups as necessary. The seeded areas will be monitored throughout the spring to ensure proper turf establishment.
    • Replacement tree and landscape plantings.
  • Construction Substantial Completion Update

    Share Construction Substantial Completion Update on Facebook Share Construction Substantial Completion Update on Twitter Share Construction Substantial Completion Update on Linkedin Email Construction Substantial Completion Update link

    The project is now considered substantially complete. The contractor will address the following remaining items in the spring of 2024.

    • Sanitary sewer lining (winter)
    • Remaining Irrigation repairs
    • Topsoil regrading, seeding and hydromulch touch ups as necessary. The seeded areas will be monitored throughout the spring to ensure proper turf establishment.
    • Replacement tree and landscape plantings.
    • Warranty repairs

    The sidewalk snow and ice removal is the responsibility of the property owner.

    The City of Edina and GMH Asphalt thank you for your patience and cooperation throughout the 2023 construction season.

  • Construction Update - 11/9/2023

    Share Construction Update - 11/9/2023 on Facebook Share Construction Update - 11/9/2023 on Twitter Share Construction Update - 11/9/2023 on Linkedin Email Construction Update - 11/9/2023 link

    Project Wide

    • The final asphalt pavement layer is complete.
    • Topsoil installation will continue the week of 11/13, along with seeding. The seed will be evaluated in the spring for effectiveness.
    • Irrigation repairs have been suspended for the winter. If your irrigation system was not repaired, reach out to Nina for the next steps.
    • Landscape plantings and trees have been suspended until next spring. If you have not already done so, please reach out to Nina with any landscaping items remaining to be installed/delivered to your property in the spring.
    • Permanent signs and pavement markings are scheduled to be installed the week of 11/13.


    Kipling Ave and Grimes Ave

    • Sanitary sewer cleaning, televising, and lining will continue and is scheduled to be completed by the end November.


  • Construction Update - 11/3/2023

    Share Construction Update - 11/3/2023 on Facebook Share Construction Update - 11/3/2023 on Twitter Share Construction Update - 11/3/2023 on Linkedin Email Construction Update - 11/3/2023 link

    Phase 2: Monterey Ave and Lynn Ave

    • Topsoil installation will continue the week of 11/6, along with dormant seeding. The dormant seed will be evaluated in the spring for effectiveness.


    Phase 3: Kipling Ave and W 40th St

    • Asphalt driveway restoration is complete.
    • Topsoil installation will continue the week of 11/6, along with dormant seeding. The dormant seed will be evaluated in the spring for effectiveness.


    Project Wide

    • The final asphalt layer is scheduled for mid-week the week of 11/6.
      • Check your front door for parking and driveway access.
      • The asphalt can be driven on following final compaction rolling.
    • Irrigation repairs have been suspended for the winter. If your irrigation system was not repaired, reach out to Nina for the next steps.
    • Landscape plantings and trees have been suspended until next spring. If you have not already done so, please reach out to Nina with any landscaping items remaining to be installed/delivered to your property in the spring.


  • Construction Update - 10/27/2023

    Share Construction Update - 10/27/2023 on Facebook Share Construction Update - 10/27/2023 on Twitter Share Construction Update - 10/27/2023 on Linkedin Email Construction Update - 10/27/2023 link

    Phase 1: Grimes Ave and Inglewood Ave

    • Irrigation system repairs at corner lots resumed. Please contact Nina if you have issues with your system.


    Phase 2: Monterey Ave and Lynn Ave

    • Topsoil installation began and will continue the week of 10/30, along with dormant seeding. The dormant seed will be evaluated in the spring for effectiveness.
    • Irrigation system repairs began and will continue through the week of 10/30. Please reach out to Nina if your system has not been repaired.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details if you haven’t done so already.


    Phase 3: Kipling Ave and W 40th St

    • The concrete sidewalk is complete.
    • The base layer of asphalt is complete.
    • Asphalt driveway restoration is complete.
      • Full asphalt driveways being done by private contract are scheduled to be completed the week of 10/30.
    • Irrigation system repairs began and will continue through the week of 10/30. Please reach out to Nina if your system has not been repaired.
    • Topsoil installation began and will continue the week of 10/30, along with dormant seeding. The dormant seed will be evaluated in the spring for effectiveness.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details if you haven’t done so already.


    Project Wide

    • The final asphalt layer is scheduled for mid-week the week of 11/6.


Page last updated: 08 Jul 2024, 04:22 PM