Construction Update - 11/9/2023

Project Wide

  • The final asphalt pavement layer is complete.
  • Topsoil installation will continue the week of 11/13, along with seeding. The seed will be evaluated in the spring for effectiveness.
  • Irrigation repairs have been suspended for the winter. If your irrigation system was not repaired, reach out to Nina for the next steps.
  • Landscape plantings and trees have been suspended until next spring. If you have not already done so, please reach out to Nina with any landscaping items remaining to be installed/delivered to your property in the spring.
  • Permanent signs and pavement markings are scheduled to be installed the week of 11/13.


Kipling Ave and Grimes Ave

  • Sanitary sewer cleaning, televising, and lining will continue and is scheduled to be completed by the end November.


Share Construction Update - 11/9/2023 on Facebook Share Construction Update - 11/9/2023 on Twitter Share Construction Update - 11/9/2023 on Linkedin Email Construction Update - 11/9/2023 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>