Construction Update - 11/9/2023
Project Wide
- The final asphalt pavement layer is complete.
- Topsoil installation will continue the week of 11/13, along with seeding. The seed will be evaluated in the spring for effectiveness.
- Irrigation repairs have been suspended for the winter. If your irrigation system was not repaired, reach out to Nina for the next steps.
- Landscape plantings and trees have been suspended until next spring. If you have not already done so, please reach out to Nina with any landscaping items remaining to be installed/delivered to your property in the spring.
- Permanent signs and pavement markings are scheduled to be installed the week of 11/13.
Kipling Ave and Grimes Ave
- Sanitary sewer cleaning, televising, and lining will continue and is scheduled to be completed by the end November.