Construction Update - 6/23/2023
Phase 1: Grimes Ave and Inglewood Ave
- A select number of trees are scheduled to be removed during the week of 6/26.
- Water main improvements will continue into the week of 6/26. The contractor will then begin replacing water service pipes.
- Roadway excavation and gravel installation is tentatively scheduled to begin in the middle of July.
- Check your front door daily for temporary loss of driveway access.
Phase 2: Monterey Ave and Lynn Ave β Work tentatively scheduled to begin in July
- A select number of tree removals will be completed in concurrence with Phase 1 tree removals, scheduled to occur during the week of 6/26.
- The contractor is scheduled to begin reclaiming the roadways in the middle of July. Reclaiming is the process of grinding the existing asphalt into a gravel base and is anticipated to take 1-2 days to complete.
Phase 3: Kipling Ave and W 40th St β Work tentatively scheduled to begin in August
- A select number of tree removals will be completed in concurrence with Phase 1 tree removals, scheduled to occur during the week of 6/26.