Construction Update - 6/30/2023

The Contractor will NOT be working Monday 7/3 or Tuesday 7/4.
Phase 1: Grimes Ave and Inglewood Ave
- Tree removals complete.
- Water main improvements will be completed by 6/30. Residents currently on temporary water service will be returned to full service starting the week of 7/3.
- Storm sewer improvements to begin the week of 7/3.
- Roadway excavation and gravel installation is tentatively scheduled to begin by mid-July.
- Check your front door daily for temporary loss of driveway access.
Phase 2: Monterey Ave and Lynn Ave Work tentatively scheduled to begin 7/10
- Tree removals complete.
- The contractor is scheduled to begin reclaiming the roadways the week of 7/10. Reclaiming is the process of grinding the existing asphalt into a gravel base and is anticipated to take 1-2 days to complete.
Phase 3: Kipling Ave and W 40th St – Work tentatively scheduled to begin in August
- Tree removals complete.
Have a happy and safe 4th of July!