Construction Update - 7/21/2023

Phase 1: Grimes Ave and Inglewood Ave

  • All utility work is complete.
  • Roadway excavation and gravel installation is scheduled to begin the week of 7/31.
  • Excavation to replace poor soils with stable soils under the roadway and gravel is expected to be significant on the south half of Phase 1. Check your front door daily for temporary loss of driveway access.


Phase 2: Monterey Ave and Lynn Ave

  • Removal of concrete curb and gutter and driveway aprons will continue into week of 7/24.
  • Please recall the watermain and water services will not be replaced along the north half of Monterey Avenue. The main and services are owned by the City of St. Louis Park.
  • Temporary water setup is complete for homes on the north half of Lynn Avenue. Homes have been transferred to temporary watermain service.
  • The south half of Lynn Ave and all of Monterey Ave will not be placed on temporary water service. However, properties in this area will experience short term shut offs ranging from 4-8 hours. Check your front door daily for date and duration of shut off.
  • Water main improvements will continue the week of 7/24.
  • Storm sewer and sump drain installation will follow water main improvements.
  • Check your front door daily for temporary loss of driveway access.


Phase 3: Kipling Ave and W 40th St – Work tentatively scheduled to begin in early/mid-August