Construction Update 8/25/2023

Phase 1: Grimes Ave and Inglewood Ave

  • Concrete sidewalk installation and the base layer of asphalt paving is complete.
  • Irrigation system repairs will begin the week of 8/28. Please contact Nina if you have a system that needs to be restored.
  • Topsoil installation is scheduled to begin the week of 8/28.
  • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details.


Phase 2: Monterey Ave and Lynn Ave

  • Roadway excavation and gravel installation began and will continue the week of 8/28.
  • Excavation is anticipated to be deep on the south half of Lynn Ave and Monterey Ave. This work will take approximately 2-3 days to complete once the contractor begins in this area. Temporary loss of driveway access and traffic delays are to be expected. Driveway access will be restored at the end of each workday. Please contact Nina if you need special assistance or concerns during this work.
  • Concrete curb and gutter, driveway aprons, and sidewalk work is scheduled to begin soon after the Labor Day holiday.


Phase 3: Kipling Ave and W 40th St

  • Dewatering began the week of 8/21. Dewatering is the process of lowering the underground water table which is needed to complete the underground utility installations.
    • This process requires the use of a generator which will run 24 hours a day, 7 days a week until the work is completed. This work will take approximately 2 weeks to complete.
  • Following temporary water setup, the utility subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary water main.
  • Water main improvements will begin the week of 8/28.
  • Water service installation will begin following the completion of water main installation.
  • Storm sewer and sump drain installation will begin following the completion of water main improvements.