  • GMH Asphalt began work on 5/9.
  • The contractor is scheduled to reclaim Lynn Ave, Littel St, Oakdale Ave (both segments), and Branson St on 5/12. Reclaiming is the process of grinding the existing asphalt into an gravel base.
  • Removal of curb and gutter, sidewalk, and driveway aprons will begin as necessary in preparation for the underground utility work.
  • Watermain related work is scheduled to begin the week of 5/16.
  • We invite you to review this document summarizing what to expect during construction.


As construction begins in your phase, we would like to continue to stress the importance of checking your front door daily for time sensitive notifications.