Construction Resumes! Project Update 4/13/2023

The contractor will return to site on 4/17 to resume work on West 42nd Street. Additional information on the remainder of the project area will be posted soon.

West 42nd Street - Utility Work Wrap Up

  • The contractor is scheduled to complete the watermain work on the street during the week of 4/17.
    • There will be a short term water shutoff for this work.
    • Check your front door daily for notification of this work.
    • Anticipate a road closure at the intersection of Kipling Avenue during the watermain work.
  • Sump drain installation is scheduled for the week of 4/17 and is anticipated to last for 2 days. During this work expect a short term (<45 minute) loss of driveway access.
  • After the sump drain installation, crews will finish installing the storm sewer that was nearly completed last fall. This work is anticipated to be complete during the week of 4/24.
  • Following the underground utility work, crews will reclaim the asphalt pavement in preparation for roadway excavation and gravel installation.


As construction resumes in your phase, we would like to continue to stress the importance of checking your front door daily for time sensitive notifications.